Provision of off-grid PV Systems in Six Governorates in Republic of Yemen for 63 Facilities
UNOPS
Provision of off-grid PV Systems in Six Governorates in Republic of Yemen for 63 Facilities
Request for quotation
Reference:
RFQ/2019/11036
Beneficiary countries:
Yemen
Registration level:
Basic
Published on:
01-Aug-2019
Deadline on:
25-Aug-2019 09:00 0.00
Description
Tender description: Provision of off-grid PV Systems in Six Governorates in Republic of Yemen for 63 Facilities as further discriped on RFQ_Section_II_Schedule of requirements and Bill of Quantity (BoQ).
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
This tender has been posted through the UNOPS eSourcing system. Cet avis a été publié au moyen du système eSourcing de l'UNOPS. Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS.
Link | Description | |
---|---|---|
https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
26131507
-
Solar power plants
New clarification added: Dear Bidder,Please note the below raised questions and our official responses in connection to the Request for Quotation, ref. RFQ/2019/11036: Question (1): Section III returnable quotation seems to bear a different RFQ Number. Please indicate the correct number.Answer (1): Corrected. please refer to the RFQ documents, the RFQ number is RFQ/2019/11036.Question (2): Due to long Eid holidays, we would appreciate if you postpone the deadline at least for a week. Thanks for consideration.Answer (2): Please note that goods/works in this RFQ are required immediacy for emergency; deadline cannot be extended, and in case the deadline is extended, bidders will be notified.Question (3): The Bank Guarantee format states there is a guarantee reduction after "Taking Over Certificate" until issue of "Final Completion Certificate" Is the Final Completion Certificate issued on handover of all sites or is it only to be issued after completion of the full 2 years warranty/maintenance period? ie is the guarantee to remain open for over 2 years?"This Bank Guarantee for Performance ("Guarantee") is valid and will continue to be valid from the date of this letter for the Guaranteed Sum and will reduce to [2.5 or 5: select one]% of the Contract Price upon the issue of the Taking Over Certificate. This Guarantee will automatically become null and void on the issue of the Final Completion Certificate or, if a dispute arises under the Contract, after the final determination of that dispute, whichever occurs later."Answer (3): Please note that the Final Completion Certificate will be issued within 28 days after the latest of the expiry dates of the Defects Notification Periods,For the contract that will be signed as a result from this RFQ the DNP is 12 months, for more details please refer to Clause number 9.4 in the contract template in RFQ document section This shall form part of the official solicitation documents. Please be guided accordingly.
Edited on:
11-Aug-2019 20:20
Edited by:
webservice@unops.org
New amendment added #1: Updating the following document:- RFQ_Section_III_Returnable_Quotation_Schedules - For all Lots - Part (1).- RFQ_Section_III_ Technical Questionnaire - For all Lots - Part (2).- RFQ_Section_II_Schedule_of_Requirements - For all Lots (correcting the RFQ reference only).
Edited on:
07-Aug-2019 15:33
Edited by:
webservice@unops.org