New clarification added: part 2: 10. Removal of third floor washbasins. Background. The third floor architectural demolition schedule lists eight washbasins, while the water supply and drainage demolition schedule lists five. The BOQ allows for removal of five washbasins. Request. Please check the quantities and locations of the fixtures to be removed in the architectural and water supply and drainage designs. Please also confirm the scope of removal and reinstatement of existing vertical pipelines of water supply and sewage. 11. Silencer and duct fitting dimensions for P1. Background. The P1 (П1) specification gives the silencer and one bend as 500 × 300 mm. The BOQ describes the silencer as 500 × 200 mm and the bend as 400 × 200 mm, while the straight 500 × 300 mm duct section and other fittings of that size remain unchanged. Request. Please provide a coordinated installation drawing for P1 showing the dimensions of the silencer and all duct fittings. Reference. First floor heating and ventilation design (OV1), PDF pp. 5 and 8; BOQ WP1 items 549 and 560, rows 643 and 654. 12. Toilet extract system designations and shared vertical duct. Background. The third floor diagrams identify the extract system as “В3”, while the heading of its specification identifies it as “В2”. The first and third floor diagrams show connections to the second floor ductwork. Request. Please reconcile the system designations, design airflows and equipment tags. Please identify the scope boundaries and condition of the shared second floor ventilation riser, the works required to it, and the arrangements for balancing and testing the systems separately. Reference. OV1, PDF p. 6; third floor heating and ventilation design (OV3), PDF pp. 3–6; BOQ WP1 rows 697–714 and WP2 rows 573–593. 13. Extract outlet height and roof penetration. Background. The first floor ventilation plan requires the Ø250 duct to terminate 0.5 m above the roof, while the МВ1 diagram shows the outlet 2 m above the roof. The roofing works belong to a different lot. Request. Please confirm the final outlet elevation and location, supports, fixings and roof penetration detail. Please define the allocation of work and materials between the lots and the installation sequence required to keep the roof watertight. 14. Reinstatement of heating after removal of 69 radiators. Background. The architectural design and BOQ provide for removal of 69 bimetallic radiators on the third floor. The heating and ventilation design and BOQ include the supply and installation of only two new steel radiators for the toilet areas. A separate item for reinstalling the removed radiators has not been identified. Request. Please identify which radiators are to be retained and reinstalled, which are to be replaced, and who is responsible for restoring heating in the remaining rooms. If this work belongs to Lot 1, please add the necessary installation, valves and fittings, connections, flushing and testing to the design and BOQ. 15. Kitchen ventilation. Background. The kitchen diagram specifies МВ1 extract at 3,350 m³/h from three hoods and П1 supply at 2,200 m³/h. ПВ1 serves adjacent rooms, and part of the additional make-up air is to enter through air transfer paths between rooms. A complete coordinated control scheme is not provided. Request. Please provide a room air balance showing transfer airflows and the operating modes of all units. Please clarify the scope of controls, damper operation, regulation and required air transfer devices, and reflect these in the specification and BOQ. Please show the hood locations and identify who is to provide openings required for ducts, supports and penetrations, and include them in the BOQ where required. 16. Luminaire types and emergency lighting. Background. For the ДБО02ВСП emergency luminaires, the electrical specifications refer to version “б”, while the BOQ refers to version “а”. For the 30 W S66-3340-V21 luminaire on the third floor, the BOQ states surface mounting, whereas the S66 designation and the design specifications refer to recessed luminaires. Request. Please reconcile the full luminaire designations, mounting method and type of emergency power supply for each luminaire. Reference. First floor electrical design (ETR1), PDF p. 28; ETR3, PDF p. 17; BOQ WP1 rows 844–846 and WP2 rows 624 and 628–630. 17. Cable tray and fitting covers. Background. For 100 × 300 mm cable trays, the BOQ lists 200 mm wide covers, code 35524: 117 m on the first floor and 111 m on the third floor. The electrical specifications instead require 300 mm covers, code 35525. Cover codes also differ for some bends. Request. Please reconcile the cover widths and codes for straight sections, bends and branches with the tray widths, and correct the BOQ. Reference. ETR1, PDF p. 30; ETR3, PDF p. 18; BOQ WP1 rows 920–921 and 927–928; WP2 rows 679–680 and 682–683. 18. Lifting equipment list and supply of the vertical platform. Background. The BOQ includes two inclined FIL150 platforms. The architectural design also shows a bespoke vertical platform rated at 0.55 kW at shelter entrance No. 1. A separate supply item for this platform has not been identified in either lot’s BOQ. Request. Please provide a complete lifting equipment list with quantities and corresponding plan tags. Please identify the lot to which the vertical platform belongs and the BOQ items covering its supply, installation and builders’ work; add the necessary items where missing. Please explicitly confirm whether a separate goods lift is required. 19. Technical specification for the vertical platform. Background. The plan states the vertical platform’s purpose, individual configuration and power rating of 0.55 kW. A complete specification and section showing its travel and stops have not been identified. The BOQ lists functions and materials for FIL150, but does not define the vertical platform’s supply scope or configuration. Request. Please provide a technical specification for the vertical platform, including its supply scope and configuration. Kind regards,_________ Dear Bidder, Thank you for your questions. Please see the following document with answers added in the Documents Section: RFQ_2026_65003_Questions and Answers.pdf. As a result, the Bill of Quantities for Lot 1 was updated to reflect the changes caused by the yout questions. Please use the updated "RFQ_2026_65003_BОQ_LOT_1_Schedule_4.1.A_rev.1.xls" in the Documents Section. The changes are highlighted in green for your convenience. Best regards, UNOPS Procurement Team
Edited on:
13-Nov-2026 10:21
Edited by:
webservice@unops.org
New clarification added: Dear UNOPS Procurement team,Please consider our request for clarification on Lot 1 / part 1: 1. Heating availability and conditions for finishing works. Background. The period for internal finishing works includes winter. The availability of a heat source and the ability to maintain the required temperature and humidity affect wet finishing works to floors and walls. Request. Please identify who is responsible for keeping the heating system operational and maintaining the required temperature. Is it technically possible to provide local heating in the Lot 1 areas if the central heating system is not operating, and what heat source can be used? Please confirm whether draining and refilling the shared heating systems, restoring heating and temporarily heating the Lot 1 areas should be included in the Contractor’s overheads. 2. Coordination between contractors. Request. Please explain how the activities of the contractors working at this site will be coordinated and confirm whether UNOPS is responsible for this coordination. 3. Testing and separate handover of Lot 1. Background. Lot 1 includes building works, lifting equipment and engineering systems. Some of these systems connect to networks outside the areas covered by Lot 1. A defined scope of testing and handover documentation is therefore needed. Request. Please identify who will arrange and pay for independent inspections and tests of the shared building systems. Please specify the equipment passports, manuals, staff training, spare parts and maintenance obligations required for the separate handover of Lot 1, given that its engineering systems form part of the building’s overall systems and works outside the Lot 1 scope are not assigned to the Lot 1 Contractor. Reference. Sections II–V, Schedules 3.2.C and 3.2.G–H, PDF pp. 18–20 and 22; architectural, water supply and drainage, heating and ventilation, electrical and structured cabling specifications; equipment testing and commissioning requirements. 4. Movement joint materials. Background. The architectural design specifies Ceresit CS 51 polyurethane sealant and a Ø6 mm backer rod: 90.14 m on the first floor, 355.84 m on the third floor and 12 m in the perimeter paving. The BOQ lists Ceresit TS 51 expanding foam, and the backer rod for the floor joints is described as 50 mm. Request. Please confirm the joint filling material, backer rod diameter, joint cross section and sealant consumption. Please coordinate the material descriptions and quantities in the BOQ and design. Reference. First floor architectural design (AR1), PDF p. 16; third floor architectural design (AR3), PDF p. 17, sheet 8; façade design, PDF p. 20, sheet 14; BOQ WP1 rows 293–295, WP2 rows 60–62 and WP3 rows 82–84. 5. Sports floor construction and boarding volume. Background. The architectural design specifies Grabo JumpAir Elite Unique Oak 2250 × 190 × 14 with an overall system thickness of 44 mm, as well as subfloor boarding, joists and brick piers. The boarding is specified as 40 mm thick, with an area of 269.96 m² and a volume of 9.44 m³. However, 269.96 m² multiplied by 40 mm gives approximately 10.80 m³.Request. Please confirm which layers are included in BOQ items 143–144 to avoid double counting. Reference. AR1, PDF pp. 10 and 16, sheets 2.1 and 7; BOQ WP1 items 138–144. 6. Skirting to KOUTEX epoxy flooring. Background. For the workshop room, the architectural design specifies 1.5 mm KOUTEX flooring over 70.20 m². It also specifies 80 mm high skirting around the perimeter, measured in linear metres, with the floor finish continued up the walls. Request. Please specify the skirting material and confirm whether the epoxy floor coating is to be continued up the walls. 7. Profiles and plasterboard lining. Background. The BOQ describes the CW50 profile as “6 mm” and the UD27 profile as “3 mm” (see the screenshot referenced below). Request. Please confirm the actual metal thicknesses, profile types and spacing, infill and required performance of these constructions. Please provide typical details and correct the thickness descriptions in the BOQ. Please specify the required fire resistance, sound insulation and plasterboard type for each area: standard, moisture resistant, fire resistant or reinforced. Reference. AR1, PDF p. 16; AR3, PDF pp. 21 and 23; BOQ WP1 rows 196–200 and 243–247; WP2 rows 306–313. Screenshot: https://prnt.sc/yOKUIsBBTqqO. 8. Window replacement scope. Background. The architectural design includes window schedules and instructions to replace damaged windows. The Lot 1 BOQ includes removal of certain windows, window sills, external sill flashings and making good the reveals. Separate items for the supply of new window units have not been identified. Request. Please confirm whether window replacement is included in Lot 1 or in a separate scope of works. Please identify the corresponding BOQ items or add the required supply and installation items. 9. Third floor water heater types and power ratings. Background. The water supply design specifies four Ariston DUNE RS30 water heaters rated at 1,500 W each and one Atlantic Steatite Elite VM050 rated at 1,500 W. The BOQ instead lists four Atlantic PC30 units and one Atlantic Slim PC50, all rated at 2,000 W each. The combined installed power of these five units therefore differs by 2.5 kW. Request. Please confirm the final water heater models and specifications, coordinate them with the electrical design and correct the BOQ. Please provide a room by room schedule showing each unit’s storage capacity, power rating, connection arrangement and protective devices if needed. Reference. Third floor water supply and drainage design (VK3), PDF p. 5, specification sheet 1; BOQ WP2 items 1332–1333, rows 513–514; third floor electrical design (ETR3), plans and circuit diagrams. _________ Dear Bidder, Thank you for your questions. Please see the following document with answers added in the Documents Section: RFQ_2026_65003_Questions and Answers.pdf. As a result, the Bill of Quantities for Lot 1 was updated to reflect the changes caused by the yout questions. Please use the updated "RFQ_2026_65003_BОQ_LOT_1_Schedule_4.1.A_rev.1.xls" in the Documents Section. The changes are highlighted in green for your convenience. Best regards, UNOPS Procurement Team
Edited on:
13-Nov-2026 10:18
Edited by:
webservice@unops.org
New amendment added #3: Dear Bidders, Based on the questions raised during the solicitation period, the following document is added in the Documents Section: RFQ_2026_65003_Questions and Answers.pdf. As a result, the Bill of Quantities for Lot 1 was updated to reflect the changes caused by the bidders' technical questions. Please use the updated "RFQ_2026_65003_BОQ_LOT_1_Schedule_4.1.A_rev.1.xls" in the Documents Section. The changes are highlighted in green for your convenience. No other changes have been made in the RFQ. Best regards, UNOPS Procurement Team
Edited on:
13-Nov-2026 10:13
Edited by:
webservice@unops.org
New amendment added #2: Dear Bidders, Please be informed that UNOPS received a number of clarification requests, answers to which will be published shortly. In order to accommodate the upcoming clarifications in your bids, this RFQ is extended as follows: 1. Bid Submission Deadline is extended until 20 November 2026; 2. Deadline for Clarifications is extended until 13 November 2026. No other changes have been made in the RFQ. Best regards, UNOPS Procurement Team
Edited on:
10-Nov-2026 16:12
Edited by:
webservice@unops.org
New amendment added #1: Dear Bidders, Please be informed that the following documents are published in the Documents section: Pre-Bidding Meeting Minutes (please refer to the document "RFQ_2026_65003_Pre-Bidding Meeting Minutes.pdf"); Site Visit Minutes (please refer to the document "RFQ_2026_65003_Site Visit Minutes.pdf"). No other changes have been made in the RFQ. Best regards, UNOPS Procurement Team
Edited on:
06-Nov-2026 09:59
Edited by:
webservice@unops.org
New clarification added: Dear Tender Team. Hereby our Company confirms its intention to take part in the pre-tender clarification meeting under the procurement procedure RFQ/2026/65003, scheduled for October 30, 2026 at 11:00 (Kyiv time). Please send the link to connect to the Google Meet virtual meeting to the following representatives of our company. ___________ Dear Bidder, Thank you for interest in this tender. Please see below the link to the Pre-Bidding Meeting on 30 October 2026 at 11:00 am (Kyiv time): meet.google.com/kqs-minq-udi Best regards, UNOPS Procurement Team
Edited on:
30-Oct-2026 08:57
Edited by:
webservice@unops.org
New clarification added: Доброго дня. Ми маємо намір прийняти участь у тендері, також просимо надіслати нам посилання на онлайн зустріч, та ми плануємо відвідати 03.11.2026 об'єкт згідно наданої інформації у тендері. ___________ Dear Bidder, Thank you for interest in this tender. Please see below the link to the Pre-Bidding Meeting on 30 October 2026 at 11:00 am (Kyiv time): meet.google.com/kqs-minq-udi Also, your representatives will be accompanied by UNOPS Engineers during the site visit on 3 November 2026. Please note that the language of communications is English. Best regards, UNOPS Procurement Team
Edited on:
30-Oct-2026 08:56
Edited by:
webservice@unops.org
New clarification added: Dear UNOPS Procurement Team,Our firm confirms its participation in the clarification (pre-bid) meeting for RFQ/2026/65003 – Light repairs of the building of the Snihuriv Lyceum, Snihurivka (Lot 1 and Lot 2), scheduled for 30 October 2026 at 11:00 Kyiv time via Google Meet.Please register representatives of our company.Thank you for your cooperation.___________ Dear Bidder, Thank you for interest in this tender. Please see below the link to the Pre-Bidding Meeting on 30 October 2026 at 11:00 am (Kyiv time): meet.google.com/kqs-minq-udi Best regards, UNOPS Procurement Team
Edited on:
30-Oct-2026 08:53
Edited by:
webservice@unops.org
New clarification added: Good afternoon!Our company would like to participate in the pre-tender meeting.___________ Dear Bidder, Thank you for interest in this tender. Please see below the link to the Pre-Bidding Meeting on 30 October 2026 at 11:00 am (Kyiv time): meet.google.com/kqs-minq-udi Best regards, UNOPS Procurement Team
Edited on:
30-Oct-2026 08:52
Edited by:
webservice@unops.org
New clarification added: Dear Sir/Madam,Our company kindly requests you to provide the link to the online pre-bid clarification meeting scheduled for 30 October 2026 at 11:00 AM Kyiv time via Google Meet.Thank you in advance for your response.___________ Dear Bidder, Thank you for interest in this tender. Please see below the link to the Pre-Bidding Meeting on 30 October 2026 at 11:00 am (Kyiv time): meet.google.com/kqs-minq-udi Best regards, UNOPS Procurement Team
Edited on:
30-Oct-2026 08:51
Edited by:
webservice@unops.org
New clarification added: Dear UNOPS Procurement Team, Please consider our company for a clarification on-line pre-bid meeting as follows: Date: 30 October 2026 Time: 11:00 am Kyiv time Location: Virtual meeting via GoogleMeet.(on-line only) Kind regards, ___________ Dear Bidder, Thank you for interest in this tender. Please see below the link to the Pre-Bidding Meeting on 30 October 2026 at 11:00 am (Kyiv time): meet.google.com/kqs-minq-udi Best regards, UNOPS Procurement Team
Edited on:
27-Oct-2026 16:47
Edited by:
webservice@unops.org
New clarification added: Dear UNOPS Procurement Team,With reference to RFQ/2026/65003 "Light repairs of the building of the Snihuriv Lyceum, Snihuriv City Council, Bashtansky district, Mykolaiv region, Ukraine", our company hereby confirms its participation in:The Site Inspection on 03 November 2026 at 10:00 Kyiv time at the Snihuriv Lyceum, 17 Nezalezhnosti St., Snihurivka, Bashtansky district, Mykolaiv region.Kind regards, ___________ Dear Bidder, Thank you for interest in this tender. UNOPS Engineers will accompany your representatives on site on 3 November 2026 at 10:00 am Kyiv time. Best regards, UNOPS Procurement Team
Edited on:
27-Oct-2026 16:45
Edited by:
webservice@unops.org