New amendment added #1: Dear Bidders,Please note that following changes to the tender ITB/2026/62687:The tender deadline has been exteded to 07 Sep 2026 The clarification deadline has been extended to 02 Sep 2026.Form C and D have been updated to reflect signature block for all lots.
Edited on:
05-Aug-2026 16:41
Edited by:
webservice@unops.org
New clarification added: Question: We sincerely appreciate the opportunity to participate in the above-mentioned RFQ and thank you for your continued cooperation and support.To ensure full compliance with the technical and administrative requirements of the ITB, we respectfully request an extension of the bid submission deadline until 10 September 2026. This additional time will enable us to coordinate effectively with our suppliers, obtain accurate quotations, and prepare a comprehensive and competitive offer that fully complies with your specifications and requirements. We would also like to kindly request that you share the images of the items under Lot No. 1, Lot No. 2, and Lot No. 4, if available. These images would greatly assist us in accurately identifying and sourcing the required products, ensuring that our proposed items fully comply with your technical specifications and requirements. We would be grateful for your kind consideration of our request. Your support in granting the extension and providing the item images would be highly appreciated.UNOPS Response: Thank you for your interest in this RFQ and for reaching out. Please see below regarding your requests:Submission Deadline: The bid submission deadline has been extended to 07 September 2026. An official amendment detailing the revised timeline will be posted shortly on the eSourcing portal.Item Images (Lot Nos. 1, 2, and 4): We are unable to provide images for these items. To maintain strict neutrality, avoid brand or supplier bias, and ensure a fair evaluation process, bidders must rely solely on the technical specifications and detailed descriptions provided in the tender documentation.We encourage you to carefully review the technical specs in the ITB documents to ensure your proposed products comply with all requirements. Thank you
Edited on:
05-Aug-2026 16:36
Edited by:
webservice@unops.org
New clarification added: Question: Form D for the Lot requirements, only Lots 1-3 have a signature section at the bottom. Is that on purpsoe or is it required for all lots? Hi, In Form D for the Lot requirements, only Lots 1-3 have a signature section at the bottom. Is that on purpsoe or is it required for all lots?UNOPS Response: Please ensure that all lots submitted are signed. Additionally, kindly ensure that the returnable bidding forms are fully signed, as these apply to the entire tender and all lots.
Edited on:
28-Jul-2026 16:45
Edited by:
webservice@unops.org
New clarification added: Question: Form D for the Lot requirements, only Lots 1-3 have a signature section at the bottom. Is that on purpsoe or is it required for all lots? Hi, In Form D for the Lot requirements, only Lots 1-3 have a signature section at the bottom. Is that on purpsoe or is it required for all lots?UNOPS Response: Please ensure that all lots submitted are signed. Additionally, kindly ensure that the returnable bidding forms are fully signed, as these apply to the entire tender and all lots.
Edited on:
28-Jul-2026 16:44
Edited by:
webservice@unops.org
New clarification added: Question: Could you please clarify if you mean ISO 9001 or 14001? 9001 is the quality system, which if you want high quality product, is the certificate you need. 14001 is environmental, and has no bearing on product quality.UNOPS Response: Please be advised that the evaluation criteria outlined in the tender documents remain unchanged. Please refer back to the previous clarification response where we addressed a question related to this criteria.
Edited on:
08-Jul-2026 16:29
Edited by:
webservice@unops.org
New clarification added: Question: In the evaluation criteria under Sustainability criteria, it states ISO 14001 certificate is required to be submitted. ISO 14001 is a very expensive program to implemnent, and not fully suited for all companies, espcially f they are a distributor. Will the UNOPs accept an envionmental policy in lieu of 14001?UNOPS Response: In order to establish Long-Term Agreement/s for high-quality kits, we are unable to modify this requirement. However, we will accept manufacturers' ISO certifications provided they are presented by authorized distributors of the goods.
Edited on:
07-Jul-2026 19:36
Edited by:
webservice@unops.org
New clarification added: Question: So that we understand correctly, when you say 10 sets kits is this 10 kits Lot 1 or 10 Kits Lot 2 or could this be a "mix" of kits?UNOPS Response: Any PO with 10 units kit order.
Edited on:
07-Jul-2026 17:26
Edited by:
webservice@unops.org
New clarification added: Question: We note Section 2 Schedule of Requirements delivery (we assume to FCA) is called for within 30 days from an award. However, Form D Technical Bid Form indicates four - six weeks after contract signature. Please clarify which is correct.UNOPS Response: As specified in Form D (Excel file) and the Schedule of Requirements, the standard delivery timeline of 30 days upon receipt of the Purchase Order (PO) applies to orders of up to 10 units. Supplier performance will be measured against Key Performance Indicators (KPIs) based on this standard.For any orders exceeding 10 units, the delivery timeframe may extend up to six weeks. Ultimately, the actual delivery schedule remains dependent on the specific Lot and quantities requested, and will be mutually agreed upon and finalized with the selected bidder at the time of PO issuance.
Edited on:
07-Jul-2026 16:57
Edited by:
webservice@unops.org
New clarification added: Thank you
Edited on:
07-Jul-2026 15:07
Edited by:
webservice@unops.org