Supply and Delivery of Petrol and Diesel Armored Vehicles
UNOPS
Supply and Delivery of Petrol and Diesel Armored Vehicles
Request for quotation
Reference:
RFQ/2025/55801
Beneficiary countries or territories:
Israel, Palestine, State of
Registration level:
Basic
Published on:
24-Jan-2025
Deadline on:
04-Feb-2025 13:00 (GMT 0.00)
Description
Supply and Delivery of Petrol and Diesel Armored Vehicle
LOT # 1 : Petrol Armored Vehicle
LOT # 2 : Diesel Armored Vehicle
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
This tender has been posted through the UNOPS eSourcing system. / Cet avis a été publié au moyen du système eSourcing de l'UNOPS. / Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS. Vendor Guide / Guide pour Fournisseurs / Guíra para Proveedores: https://esourcing.unops.org/#/Help/Guides
First name:
N/A
Surname:
N/A
This procurement opportunity integrates considerations for at least one sustainability indicator. However, it does not meet the requirements to be considered sustainable.
Climate change mitigation and adaptation
Environmental
The tender contains sustainability considerations for preventing or minimizing damage associated with climate change.
Examples:
Energy efficiency, greenhouse gas reporting and emission offsetting.
| Link | Description | |
|---|---|---|
| https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
25101510
-
Armored motor vehicle
New clarification added: Q1. Under spare parts provisional items:1.1. Spare wheels, additional set of 4. 4 per vehicle, i.e: 16 and 20 for both types, or 4 on top of each type Petrol and diesel.UNOPS Reply: Refer to answers under Amendment No.21.2 Spare wheel full assembly or just the rubber that is required?UNOPS Reply: Refer to answers under Amendment No.2Q2. For those items decision is to be made whether or not they’re to be installed, or will be delivered separately along with vehicle (where applicable).UNOPS Reply: Refer to answers under Amendment No.2Q3. Under spares package,3.1. Dual battery system with auto split Required is system stand alone or installed into vehicle (i.e: with required options)?UNOPS Reply: Refer to answers under Amendment No.23.2 Same as above for roof mounted search light and for battery switch.UNOPS Reply: Refer to answers under Amendment No.2Q4. As per points 1.1 and 2.1 of Technical requirements, you requested TLC 300 Petrol and Diesel with Euro 0 to Euro 4 Emission standards, however, later in the same document you require: 'Quote" The vehicles must be suitable for conditions prevailing in the States of Palestine / Gaza Strip. In particular, the vehicles must conform to the road codes of this country, Gas Emission Level, and must be left-hand drive. supplier must provide all certifications and documentations required for shipping company or to obtain COGAT approval. The supplier must not commence delivery of the vehicle until UNOPS receives COGAT approval and gives the supplier the go-ahead. "Unquote"If the vehicles need COGAT approval, they must meet Euro 5 emission standards. Can you please confirm what Emission standard is required? Can you please confirm if you can obtain COGAT approval for Euro 4 vehicles? As per our knowledge, vehicles registered in Jordan and entering the State of Palestine / Gaza Strip can be Euro 4, but not vehicles entering Ashdod port to be registered through Israel. Please provide a firm and clear response?UNOPS Reply: Refer to answers under Amendment No.2.Q5. We would like to know which license plate is required in the offered vehicles?UNOPS Reply: Refer to answers under Amendment No.2Q6. Also, we would like to know if you are responsible for supplying the documentation for releasing the goods from customs? UNOPS Reply: Refer to answers under Amendment No.2Q7. LOT1 and LOT2, Protection level:Please confirm that in regards to the ballistic protection only the latest version VPAM BRV Edition 3 will be accepted?UNOPS Reply: Refer to answers under Amendment No.2Q8. LOT1 and LOT2, Protection level:Please confirm that also blast protection according to VPAM ERV is a mandatory requirement which is essential for the safety of the passengers in civilian armoured vehicles. Please confirm that only the latest version, VPAM ERV Edition 3, will be acceptedUNOPS Reply: Refer to answers under Amendment No.2Q9. LOT1 and LOT2, required option: manual deadbolts, Manual deadbolts are an outdated feature for armored vehicles with remarkable disadvantages:In case the deadbolts are not closed, the protection level of the vehicle is significantly reduced. In case the deadbolts are closed and the passengers have to be evacuated from outside, the deadbolts will be an obstacle to open the vehicle from outside. Please confirm that it is a required option that the vehicles have to be certified according to VPAM BRV and VPAM ERV without manual deadbolts in place. Otherwise please explain for what reason manual deadbolts are mandatoryUNOPS Reply: Refer to answers under Amendment No.2 Q.10 It is difficult to get a freight quote to Ashdod at the time. Can you please advise if UNOPS can provide an alternative sea port? In light of this, can UNOPS extend the due date a little further for prospective suppliers to gather alternative freight quotes?UNOPS Reply: no alternatives accepted for freight destinations, because of emergency need for the AVs UNOPS cannot extend bids submission date.Thanks,UNOPS JRS Office
Edited on:
31-Jan-2025 14:34
Edited by:
webservice@unops.org
New amendment added #2: - Please find below clarifications received & UNOPS replies to be considered in pricing & preparing the offers : Q1. Under spare parts provisional items:1.1. Spare wheels, additional set of 4. 4 per vehicle, i.e: 16 and 20 for both types, or 4 on top of each type Petrol and diesel.UNOPS Reply: Each AV except for the standard configuration, should have an extra set of wheels - 4 wheels (rim, tyre and RUN-FLAT System). It is correct that there will be 20 (5 x 4) extra spare wheels for diesel vehicles and 16 (4x4) extra spare wheels for gasoline vehicles. Spare wheels must have the same type-model and size of rim, tyre and run-flat system as will be installed on the vehicle to be ordered.1.2 Spare wheel full assembly or just the rubber that is required?Spare wheel full assembly - must have the same type-model and size of rim, tyre and run-flat system as will be installed on the vehicle to be ordered.Q2. For those items decision is to be made whether or not they’re to be installed, or will be delivered separately along with vehicle (where applicable).UNOPS Reply: Nine sets of four spare wheels for each vehicle should be delivered with the vehicle. Of course, it will not be possible to put four wheels in the trunk of a vehicle. In my opinion, spare wheels can be an additional package. The wheels must be complete, i.e. wheel rim, run-flat system and tyres.Q3. Under spares package,3.1. Dual battery system with auto split Required is system stand alone or installed into vehicle (i.e: with required options)?Dual battery system with auto split - the system must be installed by the supplier.3.2 Same as above for roof mounted search light and for battery switch.- must be installed by the supplier.Q4. As per points 1.1 and 2.1 of Technical requirements, you requested TLC 300 Petrol and Diesel with Euro 0 to Euro 4 Emission standards, however, later in the same document you require: 'Quote" The vehicles must be suitable for conditions prevailing in the States of Palestine / Gaza Strip. In particular, the vehicles must conform to the road codes of this country, Gas Emission Level, and must be left-hand drive. supplier must provide all certifications and documentations required for shipping company or to obtain COGAT approval. The supplier must not commence delivery of the vehicle until UNOPS receives COGAT approval and gives the supplier the go-ahead. "Unquote"If the vehicles need COGAT approval, they must meet Euro 5 emission standards. Can you please confirm what Emission standard is required? Can you please confirm if you can obtain COGAT approval for Euro 4 vehicles? As per our knowledge, vehicles registered in Jordan and entering the State of Palestine / Gaza Strip can be Euro 4, but not vehicles entering Ashdod port to be registered through Israel. Please provide a firm and clear response?UNOPS Reply: Suppliers can offer vehicles with emission levels 0-4, as they will not be registered in Israel and will be used only in Gaza.Q5. We would like to know which license plate is required in the offered vehicles?UNOPS Reply: AVs will not be registered in Israel and will be used only in Gaza.Q6. Also, we would like to know if you are responsible for supplying the documentation for releasing the goods from customs? UNOPS Reply: As mentioned under delivery requirements: supplier must provide all certifications and documentations required for shipping company and to obtain COGAT approval. UNOPS will obtain COGAT approval , once UNOPS receives COGAT approval the supplier will be notified to go-ahead with shipping. Q7. LOT1 and LOT2, Protection level:Please confirm that in regards to the ballistic protection only the latest version VPAM BRV Edition 3 will be accepted?UNOPS Reply: When it comes to VPAM (Association of Testing Bodies for Attack-Resistant Materials and Constructions) BRV (Ballistic Vehicle Resistance). We should stay with edition 3, which was implemented in 2021, because this choice provides optimum protection for users.Q8. LOT1 and LOT2, Protection level:Please confirm that also blast protection according to VPAM ERV is a mandatory requirement which is essential for the safety of the passengers in civilian armoured vehicles. Please confirm that only the latest version, VPAM ERV Edition 3, will be accepted.UNOPS Reply: When it comes to VPAM ERV (Explosive Resistant Vehicles) we should stay with edition 3 - like the above.Q9. LOT1 and LOT2, required option: manual deadbolts, Manual deadbolts are an outdated feature for armored vehicles with remarkable disadvantages:In case the deadbolts are not closed, the protection level of the vehicle is significantly reduced. In case the deadbolts are closed and the passengers have to be evacuated from outside, the deadbolts will be an obstacle to open the vehicle from outside. Please confirm that it is a required option that the vehicles have to be certified according to VPAM BRV and VPAM ERV without manual deadbolts in place. Otherwise please explain for what reason manual deadbolts are mandatoryUNOPS Reply: Manual deadbolts on all doors is required. This is an additional factor improving passenger protection. Using the definition of all doors - this means 5 doors (four conventional doors for passengers and one rear hatch or trunk door for cargo).- The price of the following Spare parts shall include installation, so must be installed in the vehicle by the supplier:1. Dual Battery System with automatic split, charge function and switchable to 230V DC output. (required two batteries for additional equipment e.g. radio, GPS, satellite communication).2. Roof Mounted Search Lamp (Remote to operate the direction of the roof lamp).3. Battery Switch - Master Switch.- Please consider the following under Tab "documents" in pricng: (RFQ_Section_II_Schedule of Requirements - R1) & (RFQ_Section_III_Returnable Bidding Forms - R1) All other terms, conditions, and technical specifications of the original bid shall remain the same.Best Regards,UNOPS JRS Office
Edited on:
31-Jan-2025 14:28
Edited by:
webservice@unops.org
New amendment added #1: - Extend RFQ submission date from 30 January 2025 to 04 Februray 2025 13:00 UTC.- Extend Clarification period to 30 January 2025.All other terms, conditions, and technical specifications of the original bid shall remain the same.Best Regards,UNOPS JRS Office
Edited on:
29-Jan-2025 08:31
Edited by:
webservice@unops.org