Mandate for a General Contractor for the construction of the new WIPO conference hall
Call for Expressions of Interest (EOI) No. PTD/09/051
Mandate for a General Contractor for
the construction
of the new WIPO conference hall
Please note that the deadline for the submission of proposals has been extended from Monday, December 7, 2009 to Monday, December 14, 2009. See Addendum N° 1 (in French only),downloadable below by clicking on the relevant PDF icon.*
Annex A - Consolidated List of Questions and WIPO's Answers (in French only), downloadable below by clicking on the relevant PDF icon.
Following an international architectural competition, WIPO
selected the design of Behnisch Architekten from
In December 2008, while the new construction work was
continuing, the
For this purpose, the WIPO agents (architects, engineers and
specialists) are currently drawing up the requisite documents for the
preparation and implementation of the construction phases of the project, for
which a building authorization application has already been filed with the
The new conference hall project
The project includes:
·
a new construction: the actual conference room, with a capacity of
900 seats in tiers, developed on the first floor level and including nine
interpretation booths and a control room.
The ground floor, consisting mainly of the entrance hall, is directly
connected to and opens out on to the hall of the main building (
·
changes in the existing main building, in
particular an extension to the entrance hall and the creation of additional
meeting rooms on the first floor. This
work will have to be done so as to guarantee the sound operation of existing
facilities and accessibility for WIPO staff, delegates and visitors while it is
being carried out;
·
a new construction of about 350 m2 (visitors’
access center) for the reception, monitoring and registration of WIPO delegates
and visitors.
The total volume of the project is about 31,000 m3, of which 26,000 m3 are for the conference room. The surface area is about 7,000 m2, of which 5,400 m2 are for the conference room and the total construction cost is estimated at about 50,000,000 Swiss francs. The work is scheduled to last for 24 months and to be completed in December 2012.
Taking into account the specific nature of the project, the architectural and technical features of which are specific, applicants are requested to refer to the brochure produced by the architect [please visit this page at URL http://www.wipo.int/procurement/en/notices/2009/ptd09051_f/index.html to download the architect's brochure], which deals inter alia with the following points:
· situation of the project in context;
· operation of the building;
· the idea of a sustainable building;
· the technical aspects;
· the landscaping concept.
Procedure
The launch of the request for proposals for a general contractor or a consortium is planned for March-April 2010 with the aim of starting the construction work in January 2011.
On the basis of the criteria and conditions in the annex,
and from the firms or consortia of firms that have responded to this call for
expressions of interest, an independent Selection Board, consisting of representatives
of the Member States of WIPO, will preselect, freely and without appeal, those
parties who will receive from WIPO a request for proposals and will alone be
authorized to submit a bid; no bid
submitted by a consortium other than one of those that have been preselected
will be taken into consideration.
The general contractor or consortium will also be selected subsequently, freely and without appeal, by the same independent Selection Board mentioned above.
Except for the text of this call for expressions of interest, French will be the only working language.
Any firm or consortium wishing to participate in the preselection procedure is invited to download the electronic version of the questionnaires (available only in French) by clicking below for the general contractor application form or below for the application form for a consortium of general contractors.
It is specified that the general contractor currently working on site, responsible for constructing the new administrative building, is authorized to participate in the present procedure.
WIPO wishes to draw attention to the fact that for the duration of the contract, the general contractor or consortium awarded the contract shall be entirely independent of any entity participating in the project, so as to avoid a financial or other conflict of interest arising with that participating entity, which would be detrimental to its impartiality; if that is not the case, applicants should, as a matter of course, inform WIPO accordingly at the appropriate time, as part of the request for proposals procedure.
As part of the request for proposals procedure, firms will be requested inter alia to provide, from a bank, a bid bond upon first demand and an undertaking to submit to WIPO a performance bond, also upon first demand.
For applications by consortia, firms shall indicate their individual and joint references. Each consortium may have a maximum of two general contractors. Multiple applications are forbidden and, as a result, a general contractor may participate in one consortium only.
To be taken into consideration at the preselection stage, general contractors shall satisfy the conditions of participation defined in the annex. WIPO reserves the right to verify the information provided and to request from candidates recent proof that these conditions are duly satisfied.
WIPO reserves also the right to interrupt the present procedure at any time and with complete freedom.
Candidates will receive no
compensation for participation in the preselection and selection procedures,
including in the case where the procedure is interrupted.
All questions relating to this call for expressions of interest shall be sent by electronic mail to the address: ProcurementON@wipo.int, by November 6, 2009 at the latest. The subject line of your electronic mail shall contain the reference “Call for expressions of interest No. PTD/09/051”. Beyond the above-mentioned expiry date, WIPO will be unable to respond to other questions. A summary and anonymous list of the applications received, accompanied by the responses, will be published on the WIPO Internet site (www.wipo.int/procurement/en/notices.html) by November 13, 2009 at the latest.
Submission of the expression of interest and files
The expression of interest by firms to participate in the request for proposals for the construction of the new WIPO conference hall and applicants’ files, including the duly completed and signed questionnaire and all the required documents mentioned above and in the annex, shall reach the following address by mail, fax or electronic mail (in pdf format) by *December 14, 2009:
Organisation Mondiale de la Propriété
Intellectuelle (OMPI)
Appel à manifestation d’intérêt no
PTD/09/051
Division des achats et des voyages
34 chemin des Colombettes
1211 Genève 20 – Suisse
Fax : +41 (0)22 338 8210
ANNEX
To the Call for Expressions of Interest (EOI) No. PTD/09/051
A. Preselection criteria
1. Financial capacity of the general contractor (of each individual firm in the consortium of firms) sufficient in relation to the scope of the market
Proof:
·
recent extract from the register of the Execution
Department or equivalent public authority of the country concerned, accompanied,
where appropriate, by a translation into French;
·
recent extract from the Commercial Register or
that of an equivalent public authority in the country concerned, accompanied,
where appropriate, by a translation into French;
·
the last three balance sheets and profits and
losses accounts with the reports of the auditing body, where appropriate;
· declaration concerning the annual turnover for 2006 to 2008 contained in the preselection questionnaire.
2. General references of the general contractor (of each individual firm in the consortium of firms) since January 1, 2000
Proof:
·
declaration contained in the preselection
questionnaire
3. General capacity of the general
contractor (of each individual firm in the consortium of firms) to carry out
the terms of reference open to bid
Taking into account the specific nature of the project, including primarily the construction of a conference room with specific technical features (load-bearing structure and envelope of the room made of wood with spans and overhangs of more than 30 meters), the references of the firms in the field of wooden construction and in the construction of conference rooms, concert halls or auditoria will be examined with the greatest attention.
Proof:
·
general organization chart of the general contractor;
·
profile of the general contractor;
·
declaration contained in the preselection questionnaire.
B. Conditions of participation
1. Respect for provisions on workers’ protection
Proof:
· declaration contained in the preselection questionnaire: WIPO reserves the right to request subsequent transmission of the corresponding forms of proof.
Proof:
· declaration contained in the preselection questionnaire; WIPO reserves the right to request subsequent transmission of the corresponding forms of proof.
3. Respect for equal salaries for men and women
Proof:
·
declaration contained in the preselection
questionnaire; WIPO reserves the right
to request subsequent transmission of the corresponding forms of proof.
---------------
Link | Description | |
---|---|---|
http://www.wipo.int/procurement/en/notices/2009/ptd09051_s/index.html | http://www.wipo.int/procurement/en/notices/2009/ptd09051_s/index.html | |
http://www.wipo.int/procurement/en/notices/2009/ptd09051_e/index.html | WIPO Call for EOI n° PTD/09/051 | |
http://www.wipo.int/procurement/en/notices/2009/ptd09051_e/index.html | http://www.wipo.int/procurement/en/notices/2009/ptd09051_e/index.html | |
http://www.wipo.int/procurement/en/notices/2009/ptd09051_f/index.html | http://www.wipo.int/procurement/en/notices/2009/ptd09051_f/index.html |