New amendment added #2: This amendment is done for the following reasons: 1. Under Bill Nr.5 -Transmission -El , For Item no. 4.3 , the text “ Concrete Post “ is now amended to be “ RHS post” . In addition the text " and trusts C-25" is now omitted from the BoQ. Hence in this amendment, item no. 4.3 is read as follows: Item 4.3 . Fencing with galvanized wire mesh as detailed including all intermediate straining, RHS posts ,40x40cm in concrete foundation C-20 including earth work and all associated works.NOTE: The previous amended BoQ sheet is removed and an Amendment 2- BoQ is now uploaded under the document section of the tender and Bidders must disregard the previous BoQ which they have been working on and must download and use the Amendment 2- BoQ which is now uploaded under the document section of the RFQ that has a file name “ Amendment 2- BoQ- 4.1.A Bill of Quantities & 4.1.B Daywork Schedule- RFQ_2026_61549 ''. Bidders must use this amended BoQ template to submit their financial offer both in excel and signed PDF.2. The bid submission deadline is amended to be 2026-03-03 11:00 UTCApart from the above amendment, all the parts and contents of the tender remains the same
Edited on:
27-Feb-2026 12:19
Edited by:
webservice@unops.org
New clarification added: Vendor's clarification question: upon preparation of technical document, on the solicitation document, part 4 which are key equipments proposed, the schedule requires borehole drilling rig (Rotary/DTH) and also Air Compressor in separate. However, latest machines such as our proposal (2024 model), have uniqe features that Truck mounted DTH drill rig is mounted on truck along with Air Compressor in a single truck that will satisfy your double requirement easily. Thus, our company will provide confirmation MANUFACTURE CERTIFICATE up on submission.UNOPS Response: The latest machines that combine both functions into a single unit is accaptable provided that each functions ( components )meet the capacity as stated in the solicitation documents ( I.e Air Compressor (900-1000 CFM , ≥20 bar) and the Borehole drilling rig (Rotary / DTH) with a drilling capacity of 200m.
Edited on:
27-Feb-2026 11:45
Edited by:
webservice@unops.org
New clarification added: Vendor's Clarification question: Bill Nr 5- Transmission Electrical Works requires to deliver Grundfoss SP 9-36 or equivalent Pumps. Is it required to submit the catalogue and data sheet for all electrical materials during this tendering Evaluation Phase?UNOPS response During the tending process submitting catalogues or data sheets is not required . However , the awarded contractor before delivering all the required materials should submit samples for verification and approval by the UNOPS team for alignment with the specification as confirmed in the solicitaion document & bidders submission. Vendor's Clarification question: We wouid like to require the detail about the GPRS Network from the reservoir to the pump station to effect authomatic pump start stopping system. And as far as it requires imported accessories that are not available in our country it is challenging to supply within alloted 100 days. can we therefore receive more time to fix the system after the deadlines? UNOPS response: Kindly be informed that the specification provides alternative communication options such as GPRS, Radio frequency (RF) or Direct protected signal wiring from the reservoir to the pump station. The bidder is free to select the most feasible, and technically appropriate option, provided it reliably achieves the required automatic start/stop function.Thus, bidders are expected to meet the reasonable delivery time of 100 days. Vendor's Clarification question: The fence details on the drawing and BOQ differ slightly. What kind of post did you design for the fence? Is that an RHS Post or Concrete PostUNOPS Response: The POST should be RHS Post and Not Concrete Post . Under Bill Nr.5 -Transmission -El , For Item no. 4.3 the following amendment on the BoQ will be issued shortly. Item 4.3 . Fencing with galvanized wire mesh as detailed including all intermediate straining, RHS posts and trusts C-25,40x40cm in concrete foundation C-20 including earth work and all associated works.
Edited on:
27-Feb-2026 11:35
Edited by:
webservice@unops.org
New amendment added #1: This amendment is done for the following reasons: On the BoQ - for the Bill Nr.5 -Transmission -El. a. For item no. 1 The following amendments are done . What was previously stated as “ Rated head: 159.5 m; Stages: 36 “ is now amended to be “ Rated head: 169.5 m; Stages: 36; (+/-5%)” What was previously stated as “ Flow: 10.29 m³/h; Total head: 159.5 m” is now amended to be “ Flow: 10.29 m³/h; Total head: 169.5 m; (+/-5%) “ b. For item no. 2 .5 , what was previously stated as” ….. AC and DC power source compatible ….” is now amended to be “ …. AC and DC power source compatible VFD feature ....” NOTE: The previous BoQ sheet is removed and an amended BoQ is now uploaded under the document section of the tender and Bidders must disregard the previous BoQ which they have been working on and download and use the amended BoQ which is now uploaded under the document section of the RFQ that has a file name “ Amended BoQ- 4.1.A Bill of Quantities & 4.1.B Daywork Schedule- RFQ_2026_61549''. Bidders must use this amended BoQ template to submit their financial offer both in excel and signed PDFN:B The amended texts are provided in Blue text in the amended BoQ2. The following Annexes that were provided as part of the tender documents are now removed from the amended tenders, and they are no longer part of the tender . Annex 4- Section -B Technical Specifications - Borehole - RFQ/2026/61549Annex 5- Section-A Technical Specifications - Mechanical- RFQ/2026/61549Annex 6- Section-C Technical Specifications- Solar PV System- RFQ/2026/61549Annex 7- Section-D Technical-Specification- Submersible Pump- RFQ/2026/615493. The deadline for clarification has been amended to be 2026-02-27 05:00 UTC4.The bid submission deadline has been amended to 2026-03-02 09:00 UTC5. Pre- bid presentaion slide and pre- bid minute is uploaded under the document section of the RFQ Apart from the above amendments, all parts of the tender remain the same.
Edited on:
25-Feb-2026 14:36
Edited by:
webservice@unops.org
New clarification added: Vendor's clarification questionWe refer to the Request for Quotation (RFQ) No. RFQ/2026/61549 issued for the Solar‑PV‑Powered Pumping System project. While preparing our technical and commercial proposal, we identified an inconsistency between the Bill of Quantities (BOQ) and the Technical Specifications that could affect system sizing, performance calculations, and consequently, pricing.DocumentDischarge (m³/h)Rated Head (m)BOQ (Bill Nr 5 Item 1.1)10.29 m³/h159.5 mTechnical Specifications – Annex 6, Section‑C30 m³/h194 m (under Solar‑PV system)To ensure full technical compliance and to avoid any misinterpretation in our submission, we kindly request clarification on the following points:1. Which set of discharge and head values shall be regarded as the governing parameters for the design, supply, and installation of the Solar‑PV pumping system?2. If the values in the Technical Specifications supersede those in the BOQ, should the BOQ quantities be revised accordingly, or are they to remain unchanged for cost estimation purposes?UNOPS response: Your clarification question is well noted and UNOPS will give an amendment as soon as possible and will also extend the deadline for submission to next week. We will formally notify all vendors about the specific amendment done and the specific deadline on the e-sourcing through a formal tender amendment.
Edited on:
25-Feb-2026 08:37
Edited by:
webservice@unops.org
New clarification added: Vendor's clarification question:There is no quantitiy amount put on Items in Bill Nr.5-TRANSMISSION ELECTRICAL WORK of SUBMERSIBLE PUMPS Items No 1.1 Provision and installation of electric submersible pump sets complete with motor,starter, sensor, grundfoss SP 9-36 or equivalent size and quality., POWER : 7.5 KW So please give us a caraificatio on it.UNOPS Response: Please note that under Bill Nr.5, Item no. 1.1 which is Provision and installation of electric submersible pump sets complete with motor,starter, sensor, grundfoss ... , constitutes two rows and the quantity for this item is provided in the next (second ) row as set 1. Hence as clearly stated on the second row of item no. 1.1, quantity is set 1.
Edited on:
24-Feb-2026 07:36
Edited by:
webservice@unops.org
New clarification added: Vendor's clarification request Our company is interested in this bid to participate only in the solar panel and all accessories, submersible pump supply and installation part, without the construction and borehole development. Is that possible as partial bid participation? UNOPS Response: Please note that as it is clearly stated under the particular section of the RFQ, Partial quotations shall not be allowed and Bidders must quote prices for the total goods and/or services for the total requirement requested and Evaluation will be done for the total requirement.
Edited on:
24-Feb-2026 07:25
Edited by:
webservice@unops.org