Provision of off-grid PV systems for 72 Facilities in multiple locations in Yemen (YEEAP II)
UNOPS
Provision of off-grid PV systems for 72 Facilities in multiple locations in Yemen (YEEAP II)
Request for quotation
Reference:
RFQ/2023/47709
Beneficiary countries or territories:
Yemen
Registration level:
Basic
Published on:
20-Aug-2023
Deadline on:
10-Sep-2023 06:00 0.00
Description
Provision of off-grid PV systems for 72 Facilities in multiple locations in Yemen (YEEAP II)
----------------
Lot 1: (Dhamar, Hajjah, Sa'ada and Sana'a)
Lot 2: (Ad-Dhale'e North, Amran, Ibb and Raymah)
Lot 3: (Ad-Dhale'e South, Abyan, Lahj and Hadramout)
--------------
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
----------------
Lot 1: (Dhamar, Hajjah, Sa'ada and Sana'a)
Lot 2: (Ad-Dhale'e North, Amran, Ibb and Raymah)
Lot 3: (Ad-Dhale'e South, Abyan, Lahj and Hadramout)
--------------
- The pre-bid meeting will be held on 27-August-2023 _ 02:00 pm Sana'a, Yemen time virtually via the following link: (https://meet.google.com/ctv-pjfr-dpq).
- All bidders are STRONGLY encouraged to attend the pre-bid meeting.
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
This tender has been posted through the UNOPS eSourcing system. / Cet avis a été publié au moyen du système eSourcing de l'UNOPS. / Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS. Vendor Guide / Guide pour Fournisseurs / Guíra para Proveedores: https://esourcing.unops.org/#/Help/Guides
First name:
N/A
Surname:
N/A
Link | Description | |
---|---|---|
https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
26131507
-
Solar power plants
New amendment added #3: Update in the Financial Capacity as highlighted in form: Small Works - 6 Solicitation - RFQ 04 Sections II, III, IV, V rev 1.
Edited on:
07-Sep-2023 14:58
Edited by:
webservice@unops.org
New clarification added: Question 10: Dear in item 5.0 DC Combiner Box. You have specified the following in the specifications: "DC output circuit: In accordance with the maximum current X 1.25, 1000 VDC breaker". May I ask what the maximum current is?Clarification: Please refer to the detailed drawings sheet no S1-09, the schematic diagram for more details.
Edited on:
04-Sep-2023 07:27
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Please find below the response to your clarifications:Question 1: We ask you kindly please to extend the submission period by two weeks, this is because the project is large and needs preparation for a longer period.Clarification: The deadline has been extended till 10-September-2023 9:00 AM.Question 2: Could you please extend the Deadline period?Clarification: The deadline has been extended till 10-September-2023 9:00 AM.Question 3: We would appreciate if you can extend the date of the deadline for this tender as it's a big tender and we need more time for studying it and provide you with compete prices.Calrification: The deadline has been extended till 10-September-2023 9:00 AM.Question 4: Can you extend the deadline for submission, because the project is large and needs a longer period to prepare? Also, because there are several projects that will be submitted in the same period ' three consecutive tenders ' ?Clarification: The deadline has been extended till 10-September-2023 9:00 AM.Question 5: We ask you please to extend the submission period by one or two weeks.Clarification: The deadline has been extended till 10-September-2023 9:00 AM.Question 6: Please clarify and unify the specifications of converntional fire alarm panel in in technical questionnaire it is writen "2 zones" while in BoQs is writen "4 zones".Clarification: Please refer to the updated technical questionnaire and BoQs rev1.Question 7: We ask you please to extend the submission period by one or two weeks.Calrification: The deadline has been extended till 10-September-2023 9:00 AM.Question 8: Regarding the DC cables in item 7, the required quantity is for a single core in meters, Example [(1C*6 sqr.mm) (Red & Black)] but in the material distribution summary, the required quantity -in column W in the Excel sheet- has a different description, [2(1Cx6sqr.mm)]. Shall the contractor put a consideration that one meter in the required quantity equals (1 meter of Black cable + 1 meter of Red cable) or the quantity is measured for a single core (Either Black or Red)?Clarification: Please note that the price should be according to the BOQ description as the material summary only provides more illustration for the material allocation per each facility, therfore, the quantity is measured for single core ( Eether Black or Red).Question 9: Regarding the required Roof Concrete Anchor Bolt Pull out test item 20.3, the anchor bolt will be installed directly on the old roofs, if the anchor bolt test fails due to an old and damaged rooftop reinforcement concrete, how can the contractor deal with this?Clarification: Please refer to the scope of work for more detail in the pull-out test, specificaly for your question, the test and the results of it is the responsibility of the contractor.Thank you,UNOPS Yemen.
Edited on:
31-Aug-2023 04:01
Edited by:
webservice@unops.org
New amendment added #2: Deadline Extension untill 10-September-2023 9:00 AM.Deadline Extension for clarifications untill 2-September-2023 4:00 PM.Amendments in BoQs for Lots 1, 2 and 3: rev 1.Amendment in the Technical Questionnaire: rev1.
Edited on:
30-Aug-2023 12:23
Edited by:
webservice@unops.org
New amendment added #1: Sharing the pre-bid meeting mintues held yesterday 27-August-2023.
Edited on:
28-Aug-2023 16:49
Edited by:
webservice@unops.org