RFQ Supplying, Installing, Testing, and Commissioning, Handing over of Two Generators to Aden city
UNOPS
RFQ Supplying, Installing, Testing, and Commissioning, Handing over of Two Generators to Aden city
Request for quotation
Reference:
RFQ/2019/9653
Beneficiary countries:
Yemen
Registration level:
Basic
Published on:
07-May-2019
Deadline on:
20-May-2019 09:00 0.00
Description
Tender description: RFQ Supplying, Installing, Testing, and Commissioning, Handing over of Two Generators to Aden city on RFQ_Section_II_Schedule of requirements, Bill of Quantity (BoQ), and RFQ_Section_ll_Returnable Schedules.
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
This tender has been posted through the UNOPS eSourcing system. Cet avis a été publié au moyen du système eSourcing de l'UNOPS. Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS.
Link | Description | |
---|---|---|
https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
26111601
-
Diesel generators
New clarification added: Question (5): On pages# 10@11 of your document RFQ_Section_ll_Technical Requirements-Scope of Work and Specifications - part one.docFor the title:1.16.1 Automatic Transfer Switchboard & Control Panelthere are some requirement as the following:- DC voltage.- Coolant temperature.- Oil pressure.- RPM.- Hours run.- System diagnostic.- Cycle crank.- Voltage control.Ø INDICATING LIGHTS- Low oil pressure.- High coolant temperature.- Over speed.- Fault shutdown and Fault alarms.All these features are included on the genset control panel, is it mandatory to re involve them on the ATS again or we can assume those on the genset control panel Enough ? Answer (6) : It is enough to include them in generator control panel.
Edited on:
15-May-2019 08:56
Edited by:
webservice@unops.org
New clarification added: Question (2) : Please provide us with the representative contact person to manage a site visit?Answer (2) : Kindly note that UNOPS is not responsible for arranging site visits, however, suppliers are encouraged to arrange their own site visits with each facility management. Question (3): Please let us know if we can submit our questions from us not fill to your file ?Answer (3): Please note that suppliers are required to review all bidding document and are also required to fill in all the returnable schedules and data sheets along with other documents listed in the checking list and submit them via eSourcing Question (4): Please provide us with the Environmental Code of Practice which is not included in the bid documents .Answer (4): Please note that you can refer to file attached named “Safeguard Instrument for Supply and Installation of Soundproof Generators to 1 Hospital and 1 Health Centers in Aden City.pdf” as Environmental Code of Practice in no needed Question (5): Some items in excel sheet in minus , could you clarify this situation?Answer (5): The minus sign in the BoQ is only the formula sing however, if you could please send us specific items number so we can clarify duther .
Edited on:
14-May-2019 10:39
Edited by:
webservice@unops.org
New clarification added: Question (1): Kindly clarify Item#(1.10) in Annex 2 (850-950 KVA), regarding to fuel consumption:for Genset with capacity (850-950)KVA Prime Power it is impossible to have fuel consumption of 46Lt/Hr at 100% Full Load, Kindly Clarify??? Answer (1): the fuel consumption is around 195 L/h for the DG 850-950 Kva
Edited on:
12-May-2019 12:56
Edited by:
webservice@unops.org