SUPPLY AND INSTALLATION OF SIX UNITS OF 5KVA HYBRID SOLAR INVERTER SYSTEMS IN KENEMA AND MOYAMBA DISTRICTS. SEE ATTACHED TOR & BOQ FOR DETAILS. SUBMISSION DEADLINE EXTENDED UNTIL FRIDAY 25th JULY 2025
UNICEF
SUPPLY AND INSTALLATION OF SIX UNITS OF 5KVA HYBRID SOLAR INVERTER SYSTEMS IN KENEMA AND MOYAMBA DISTRICTS. SEE ATTACHED TOR & BOQ FOR DETAILS. SUBMISSION DEADLINE EXTENDED UNTIL FRIDAY 25th JULY 2025
Request for proposal
Reference:
9198481
Beneficiary countries or territories:
Sierra Leone
Registration level:
Basic
Published on:
09-Jul-2025
Deadline on:
25-Jul-2025 10:00 (GMT 00.00)
Description
SUPPLY AND INSTALLATION OF SIX UNITS OF 5KVA HYBRID SOLAR INVERTER SYSTEMS IN KENEMA AND MOYAMBA DISTRICTS.
SEE ATTACHED TOR & BOQ FOR DETAILS.
Alhaji Sesay - srl-procurementrequests@unicef.org, Tel: +232 078525288
Email address:
srl-procurementrequests@unicef.org
First name:
Alhaji
Surname:
Sesay
Telephone country code:
Sierra Leone (+232)
Telephone number:
078525288
26131507
-
Solar power plants
26131900
-
Solar power equipment*
39111527
-
Solar lighting fixture
40101807
-
Solar heating units
41111955
-
Solar sensor
60104702
-
Solar kits
PLEASE CONSIDER BELOW IN YOUR PRICE PROPOSALS:
Number of solar panels 25 X 550 Wp
Battery Capacity 20 kW hr. DOD: 20 percent, Life So4 charging cycle 3,000.
Hybrid Inverter 2 kW
The main electrical load at PHUs (1 O2 concentrator) around 700 watts
Other loads; lighting only at nighttime main Phus and staff quarters) 75 watts (LED)
Charging station for personal gadgets: 50 watts
Other loads: electric fans (2) 200 watts.
Conservative estimate of total loads of a typical PHU at approximately 10 hours average operation is 1.5 kW equivalent to 15 kW-hr energy