RFQ Construction Contract for Small Works - Construction of 2 new Therapeutic Feeding Center (TFC) in: Yemen: At Ataq - Shabwah and Maran - Sa’adah
UNOPS
RFQ Construction Contract for Small Works - Construction of 2 new Therapeutic Feeding Center (TFC) in: Yemen: At Ataq - Shabwah and Maran - Sa’adah
Request for quotation
Reference:
RFQ/2025/56067
Beneficiary countries or territories:
Yemen
Registration level:
Basic
Published on:
12-Feb-2025
Deadline on:
02-Mar-2025 09:00 (GMT 0.00)
Description
Tender description: [RFQ Construction Contract for Small Works - Construction of 2 new Therapeutic Feeding Center (TFC) in: Yemen: At Ataq - Shabwah and Maran - Sa’adah]
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
This tender has been posted through the UNOPS eSourcing system. / Cet avis a été publié au moyen du système eSourcing de l'UNOPS. / Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS. Vendor Guide / Guide pour Fournisseurs / Guíra para Proveedores: https://esourcing.unops.org/#/Help/Guides
First name:
N/A
Surname:
N/A
Link | Description | |
---|---|---|
https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
81101513
-
Building construction management
New amendment added #2: This amendment was raised to:1. Update the BoQs for LOT 1 & LOT 2, the modified items are highlighted in red. Moreover, an explanatory sheet is attached to explain the changes made for ease of reference.The updated documents are available under the documents tab as per the below names. Bidder MUST use the latest BoQ versionBOQ of Ataq TFC LOT 1-rev.2BOQ of Maran hospital LOT 2-rev.2Explanatory sheet2. Extend tender deadline up to 2nd March 2025.Other info, terms & conditions remain the same.
Edited on:
26-Feb-2025 12:47
Edited by:
webservice@unops.org
New amendment added #1: This amendment was raised to update the BoQs for LOT 1 & LOT 2 by adding Item 5.2 to the Fire Fighting section, highlighted in red for easy reference.The updated documents are available under the documents tab as per the below names. Bidder MUST use the latest BoQ versionBOQ of Ataq TFC LOT 1-rev.1BOQ of Maran hospital LOT 2-rev.1Other info, terms & conditions remain the same.
Edited on:
25-Feb-2025 11:44
Edited by:
webservice@unops.org
New clarification added: Clarification:Dear Sir/Madam,I hope this email finds you well.Please note that regarding the buried HDPE piping as per the BOQ item 5.1 in the Fire Fighting stated that "Supply , install, test and commission HDPE (High-density polyethylene) 65mm dia." while in the drawings there is also a 50mm dia pipe for the relief pipe extended from the pumps room to the GPR tank that its quantities and size are not included in the BOQs regarding both sites.Best regards,Light Speed CompanyUNOPS REPLY:Dear Rinan,The BoQ will be updated by adding Item 5.2 in the Fire Fighting section, highlighted in red for easy reference. This will be published through the upcoming amendment (soon)
Edited on:
25-Feb-2025 08:21
Edited by:
webservice@unops.org
New clarification added: Clarification:We wish to formally bring attention to a significant concern involving inconsistencies in the firefighting system's Bill of Quantities (BOQ) and fire pump specifications. The BOQ for Item 3.1 (Fire Hose Cabinets - FHC) has excluded the landing valve, as detailed in Drawing No. FX-01-01-R0_Fire Fighting System Diagram, resulting in a discrepancy between the BOQ and the approved designs that may affect the system's functionality and adherence to standards. Furthermore, the fire pump specifications do not align with NFPA 14 requirements as outlined in the BOQs. The drawings indicate a Class III Fire Hose Cabinet System, which, according to NFPA 14 Section 7.10.1.1.1, necessitates a minimum flow rate of 500 GPM (1,893 L/min) and a pressure of 6.9 bar for the hydraulically most remote standpipe. However, the currently specified pump capacity of 100 GPM at 6.5 bar is insufficient to meet these criteria. These discrepancies collectively jeopardize the system's compliance and operational effectiveness.UNOPS REPLY:the fire hose cabinet (FHC) design includes the following features:Double Doors:The upper door is designed for use by untrained personnel. It is equipped with a restricted pressure valve calibrated to 4.5 bar, ensuring safe and manageable operation for non-professional persons.The lower door contains a 40 mm angle valve, a 3800 synthetic hose, and a 38 mm nozzle. This section is designated for use by the fire man and connects to the fire department inlet in case of fire pump failure.To ensure compliance with the BOQ, drawings, and specifications, the contractor is required to supply a fire hose cabinet meeting these criteria.Clarification:Dear UNOPS, we would like to bring to your attention that the total capacity of the indoor units for VRF01 in the INDOOR UNITS -VRF -01SCHEDULE, when calculated based on the provided drawings and BOQ for Maran Hospital, amounts to 32.20 kW. However, the required capacity for the VRF01 unit, as specified in both the drawings "CONDENSING UNITS - VRF SCHEDULE" and BOQ, is 27.7 kW. This discrepancy between the actual and required capacities needs to be addressed to ensure alignment.UNOPS REPLY:The contractor shall supply an outdoor unit with a capacity that fully complies with the total capacity of the connected indoor units, ensuring alignment with the project requirements.
Edited on:
23-Feb-2025 11:33
Edited by:
webservice@unops.org
New clarification added: Question:We refer to the Capacity form and previous experience. We intend to apply for LOT 2 only .In this case, is it compulsory to provide Two similar contracts with value of USD 800,000 for each? Or the value and number of contracts shall differ ? In other words, if we provided one similar contract with mentioned value ,a construction of a tourist hotel for private owner Is it enough?UNOPS reply:Bidders are required to refer and adhere to the evaluation criteria. Submission of one or multiple lots doesnt change the requirement.
Edited on:
19-Feb-2025 06:21
Edited by:
webservice@unops.org
New clarification added: Question:Regarding the handling of the medical gases section in both the Maran and Ateq projects, we have noticed that the bed head unit items related to the ICU are missing in the BOQ when compared to the drawings. We kindly request clarification and further information on this matter.UNOPS reply:Please note the bead head units are not included in the BOQ as they will be procured seperately not under this RFQ
Edited on:
16-Feb-2025 11:34
Edited by:
webservice@unops.org