Provision and Installation of 30 off-grid PV Solar Pumping Systems - YEEAP II
UNOPS
Provision and Installation of 30 off-grid PV Solar Pumping Systems - YEEAP II
Request for quotation
Reference:
RFQ/2023/48863
Beneficiary countries or territories:
Yemen
Registration level:
Basic
Published on:
11-Oct-2023
Deadline on:
24-Oct-2023 07:00 0.00
Description
Provision and Installation of 30 off-grid PV Solar Pumping Systems - YEEAP II
----------------
Lot 1: (Amran, Al-Bayda'a, Dhamar, Hajjah, Al-Mahweet, Sana'a)
Lot 2: (Ibb, Lahj, Taiz)
----------------
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
----------------
Lot 1: (Amran, Al-Bayda'a, Dhamar, Hajjah, Al-Mahweet, Sana'a)
Lot 2: (Ibb, Lahj, Taiz)
----------------
- The pre-bid meeting will be held on 15-October-2023 _ 02:00 pm Sana'a, Yemen time virtually via the following link: (https://meet.google.com/hky-gmes-tpx).
- All bidders are STRONGLY encouraged to attend the pre-bid meeting.
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
This tender has been posted through the UNOPS eSourcing system. / Cet avis a été publié au moyen du système eSourcing de l'UNOPS. / Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS. Vendor Guide / Guide pour Fournisseurs / Guíra para Proveedores: https://esourcing.unops.org/#/Help/Guides
First name:
N/A
Surname:
N/A
Link | Description | |
---|---|---|
https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
72141125
-
Pumping station construction service
New amendment added #3: 1. Extending the submission deadline to 24 October-2023 @ 10:00 am.
Edited on:
22-Oct-2023 07:47
Edited by:
webservice@unops.org
New amendment added #2: 1. Extending the submission deadline to 24 October-2023 @ 10:00 am.2. Revising the pre-bid meeting minutes, the revised version is: Minutes for Pre-bid Meeting RFQ_2023_48863 V1: Questions 2 & 33. Amendment in the following BoQs: a) "Lot2 - BOQs (Ibb, Lahj, Taiz)" to "Lot2 - BOQs (Ibb, Lahj, Taiz) - RevA" (sheet BOQ IBB-S1-02-A): highlighted in yellow b) "All Lots, LST-01, Quantities Distribution" to "All Lots, LST-01, Quantities Distribution, RevA: highlighted in yellow
Edited on:
19-Oct-2023 15:48
Edited by:
webservice@unops.org
New amendment added #1: 1. Sharing the pre-bid meeting minutes held on 15-October-2023.2. Amendment in the qualification criteria - Financial Capacity in the document: All Lots - Solicitation, RFQ_2023_48863 Sections II, III, IV, V REV1.
Edited on:
18-Oct-2023 08:35
Edited by:
webservice@unops.org
New clarification added: Question 5: Please note that the productivity and height of both Lots are the same while the No of Solar panels in lot 2 is less than Lot 1 which means the pumps will not operate in lot 2 .please clarify this issue?Clarification: Please note that all systems fit with the expected pumps' sizes, please stick with the quantities listed in the tender document.Question 6: We ask you kindly please to extend the submission period by two weeks, this is because the project is large and needs preparation for a longer period.Clarification: Due to the urgency of the project, it is not possible to extend the submission deadline.Regards,UNOPS Yemen.
Edited on:
17-Oct-2023 16:18
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Please find the clarifications below:Question 2: The electrical and mechanical specifications include the pump and motor specifications for item 2-1, both types of submersible pump and motor (three-phase, single-phase).However, in the Bill of Quantities (BOQ), the submersible pump is mentioned in Clause 3, but there is no mention of the motor in any lot or well. Why?Clarification: Please note that the submersible pumps must be equiped with the motor. The cost to be included in the same item.Question 3: Please clarify the following:Are motors already present in all wells? Clarification: No, motors to be supplied with the pumps, with the same specfication mentioned in the tender documents.If not, should the motor capacity be estimated based on the submersible pump and priced and its value added to the value of the submersible pump? Clarification: Yes, the cost of the BOQ item included the cost of the motor.Question 4: Does Datalogger work with internet using gprs(GSM)? Or with SD datalogger?Clarification: The inverter should have the capability for data logging and cab be extracted to external source either by internet or sim card or any onother means.
Edited on:
15-Oct-2023 09:42
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Please find the clarifications below:Question 2: The electrical and mechanical specifications include the pump and motor specifications for item 2-1, both types of submersible pump and motor (three-phase, single-phase).However, in the Bill of Quantities (BOQ), the submersible pump is mentioned in Clause 3, but there is no mention of the motor in any lot or well. Why?Clarification: Please note that the submersible pumps must be equiped with the motor. The cost to be included in the same item.Question 3: Please clarify the following:Are motors already present in all wells? Clarification: No, motors to be supplied with the pumps, with the same specfication mentioned in the tender documents.If not, should the motor capacity be estimated based on the submersible pump and priced and its value added to the value of the submersible pump? Clarification: Yes, the cost of the BOQ item included the cost of the motor.Question 4: Does Datalogger work with internet using gprs(GSM)? Or with SD datalogger?Clarification: The inverter should have the capability for data logging and cab be extracted to external source either by internet or sim card or any onother means.
Edited on:
15-Oct-2023 07:49
Edited by:
webservice@unops.org
New clarification added: Dear Bidder,Please find the clarification below:Question 1: Is it allowed to edit the quantity of solar modules to fit the total wattage if the modules larger than 550W?Clarification: No, it is not allowed.