ITB Short Form Construction Contract - Rehabilitation Works for Ministry of Education Schools in Irbid Governorate
UNOPS
ITB Short Form Construction Contract - Rehabilitation Works for Ministry of Education Schools in Irbid Governorate
Invitation to bid
Reference:
ITB/2022/40800
Beneficiary countries or territories:
Jordan
Registration level:
Basic
Published on:
17-Feb-2022
Deadline on:
13-Mar-2022 11:00 (GMT 0.00)
Description
Tender description: Rehabilitation Works for Ministry of Education Schools in Irbid Governorate
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
This tender has been posted through the UNOPS eSourcing system. / Cet avis a été publié au moyen du système eSourcing de l'UNOPS. / Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS. Vendor Guide / Guide pour Fournisseurs / Guíra para Proveedores: https://esourcing.unops.org/#/Help/Guides
First name:
N/A
Surname:
N/A
| Link | Description | |
|---|---|---|
| https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
72101501
-
Handyman services
72101504
-
Disaster proofing or contingency services
72101505
-
Locksmith services
72101506
-
Elevator maintenance services
72101507
-
Building maintenance service
72101508
-
Floor cleaning services
72101509
-
Fire protection system and equipment maintenance or repair service
72101510
-
Plumbing system maintenance or repair
72101511
-
Air conditioning installation or maintenance or repair service
72101512
-
Hoist construction service
72101513
-
Offsite construction service
72101514
-
Refuse area construction service
72101515
-
Subsidence service work
72101516
-
Fire extinguisher inspection maintenance and repair service
72101517
-
Portable generator maintenance and or repair service
72101518
-
Portable generator rental service
72101519
-
Gas fitting installation service
72101520
-
Roof framing service
72101521
-
Building framing service
New clarification added: "Reference to section 3 :CFW Labour expenses table , please inform us the quantity column cell in No.1 should be filled by monthly basis(425 workers) or should be filled for all project duration (850 workers)? and in No.3 it should be filled by (425*25%*1 month) or (425*25%*2 months)?" In order to clarify more the calculation under (Section 3 :CFW Labour expenses) table please note the following:SN#1- (The number of workers 425*60 days).SN#2- (The number of workers 425*60 days).SN#3 -The total number of workers per each lot is 425. (25%) of the workers will need transportation to be arranged by the contractor (and will be reimbursed by UNOPS), so the calculation should be based on (106 workers* 60 days). Regards,
Edited on:
10-Mar-2022 09:36
Edited by:
webservice@unops.org
New clarification added: "Reference to section 3 :CFW Labour expenses table , please inform us the quantity column cell in No.1 should be filled by monthly basis(425 workers) or should be filled for all project duration (850 workers)? and in No.3 it should be filled by (425*25%*1 month) or (425*25%*2 months)?"Please note that each bidder should fill the total number of workers for each lot 425 not 850. So to consider the total number of workers in each lot as 425, that are employed for 60 daysRegards,
Edited on:
10-Mar-2022 09:07
Edited by:
webservice@unops.org
New clarification added: "Reference to returnable bid schedule 11 ... Outline statement of proposed methods (ITB Short Form) Please clarify how this table should be filled? Taking into consideration that it is typed in the last column that the number of working months (3)please fill an example for this table since it is not clear for us, especially the quantity column." Pleas note that the example is already mentioned in the table and it shows how bidders should fill it. However, the 3 months is an example and bidders should mention 2 months not three as mentioned in the tender.Regards,
Edited on:
10-Mar-2022 06:07
Edited by:
webservice@unops.org
New clarification added: "Can we prepare the project time table line by excel?"Yes you can.Regards,
Edited on:
09-Mar-2022 11:40
Edited by:
webservice@unops.org
New clarification added: "Is there a bid entry guarantee and how much is it, as it was mentioned in the online meeting that there is no guarantee for entering the bid"Please note that bid entry guarantee "Bid security" is not requested.Regards,
Edited on:
09-Mar-2022 06:14
Edited by:
webservice@unops.org
New clarification added: "Please we need the full description for the item 76:Rail wall Guard - Scratch proof ? to give you acurate price." Please refer to the BoQ to the MDD - BoQ Tab (Modular Detailed Descriptive Bill of Quantities).
Edited on:
08-Mar-2022 12:55
Edited by:
webservice@unops.org
New clarification added: "Could you please provide the contacts to arrange visits to the sites included in the project "Rehabilitation Works for Ministry of Education Schools in Irbid Governorate"?" Please note that the sites visits are not applicable at this stage and once the contract is signed, visits to sites will be arranged.
Edited on:
08-Mar-2022 12:41
Edited by:
webservice@unops.org
New clarification added: "Could you please provide the contacts to arrange visits to the sites included in the project "Rehabilitation Works for Ministry of Education Schools in Irbid Governorate"?" Please note that the sites visits are not applicable at this stage and once the contract is signed, visits to sites will be arranged.
Edited on:
08-Mar-2022 12:35
Edited by:
webservice@unops.org
New clarification added: 1. "Are the costs of managing 425 laborers including HR and training them to be charged to the contractor price?"Yes, the contractor must include the cost of training and managing the workers.2. "Do the costs of the social security and the issuance of permits in the BOQ have to match the invoices that will be submitted at the end of each month?" The cost of the social security and work permits depends on the number of workers that are empoloyed so it can be different than the BoQ.3. "The Contractor must complete the recruitment process for CfW workers to be employed on the project within a maximum period of 30 calendar days from the start date of the contract. or from signing the contract?"During the one month Mobilization period that starts at the signing of the contract, contractor should start the recruitment process of the CfW from the list they recieve from UNOPS. 4."Are UNOPS going to give us a list of the employees or should the contractor hire employees?"UNOPS provides the workers with the list of workers to be hired. 5."The contractor is responsible for facilitating and arranging the transportation, will the laborers pay any fees? Either way, this point is not totally, could you please break it down?"The contractor should facilitate the transportation to the workers who live far away from the schools where they will be working.
Edited on:
08-Mar-2022 12:31
Edited by:
webservice@unops.org
New clarification added: 1. "I would like to ask about refugees work permits and social insurance as the ministry of labour is forcing companies to enter labourers in the social insurance for the whole period of permits not only the project period so could we issue new permits for only 3 months?" Please note that the the work permits will be issued for three months.2. "I would like to ask another qustion, does our prices for social insurance for a month or two?"Please note that the social security should be only for two months.Regards,
Edited on:
07-Mar-2022 07:22
Edited by:
webservice@unops.org
New clarification added: "Can we repeat the key personal CV'S for all lots?Can we use the same cv?"Please note that the bidder should propose a distinct project team for each LOT, sharing key personnel between the LOTs will not be acceptable, except for the Project Manager .Therefore, in regard to this criteria if the bidder provides same key personal CV's for all proposed lots, only one lot will be considered in the technical evaluation. For more details please refer to tender document (RETURNABLE BID SCHEDULE 6-PROPOSED PROJECT TEAM AND ORGANIZATIONAL STRUCTURE).Regards,
Edited on:
03-Mar-2022 14:03
Edited by:
webservice@unops.org
New amendment added #3: Please note that Amendment 3 consists of 1 clause as mentioned below.This document is considered an integral part of this ITB:Clause 1: To upload updated pre -bid minutes of meeting to Document TabAll other terms and conditions remain unchanged.
Edited on:
01-Mar-2022 10:34
Edited by:
webservice@unops.org
New clarification added: "Can the company owner be contractor's representative and project manager in the same time if he acheived the requirments?" Yes, the company owner can be the contractor’s representative and the project manager.Regards,
Edited on:
01-Mar-2022 06:48
Edited by:
webservice@unops.org
New clarification added: "Regarding the SSC for labours it required only to provide u with stamped list from SSC to sow that all labours are register?"Yes, Stamped list should be provided.Regards,
Edited on:
01-Mar-2022 06:43
Edited by:
webservice@unops.org
New clarification added: Is it required to attached the staff CV'S or only insert the names ?Yes, the staff CVs should be submitted and for more details please refere to (RETURNABLE BID SCHEDULE 6 - PROPOSED PROJECT TEAM AND ORGANIZATIONAL STRUCTURE).Regards,
Edited on:
01-Mar-2022 06:11
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Reference is made to the under subject tender (ITB/2022/40800), please find the uploaded document related to the pre -bid minutes of meeting which was held on 24 Feb 2022Regards,
Edited on:
28-Feb-2022 11:19
Edited by:
webservice@unops.org
New amendment added #2: Please note that Amendment 2 consists of 2 clauses as mentioned below.This document is considered an integral part of this ITB:Clause 1: Please find attached document: “ITB_Short_Form_Construction_Contract_Section_I_InstructionsToBidders”Clause 2: Please find attached pre -bid minutes of meeting which was held on 24 February 2022All other terms and conditions remain unchanged.
Edited on:
28-Feb-2022 10:56
Edited by:
webservice@unops.org
New amendment added #1: Please note that Amendment 1 consists of 2 clauses as mentioned below. This document is considered an integral part of this ITB.Clause 1: The deadline for bidders' clarifications is extended to be on 9 March 2022 instead of 7 March 2022Clause 2: The deadline for submitting your Bids (Tender closure) is extended to be on 13 March 2022 instead of 10 March 2022All other terms and conditions remain unchanged.
Edited on:
20-Feb-2022 13:45
Edited by:
webservice@unops.org