Renovation/Upgrading of Existing Electrical, Lighting Protection, Nurses Calling system and Extra Low Voltage Systems of Both main and New Ward Building of Korea – Sri Lanka Friendship hospital in Matara, Sri Lanka
UNOPS
Renovation/Upgrading of Existing Electrical, Lighting Protection, Nurses Calling system and Extra Low Voltage Systems of Both main and New Ward Building of Korea – Sri Lanka Friendship hospital in Matara, Sri Lanka
Invitation to bid
Reference:
ITB/2019/8398
Beneficiary countries:
Sri Lanka
Registration level:
Basic
Published on:
13-Feb-2019
Deadline on:
24-Mar-2019 09:30 (GMT 0.00)
Description
Tender description: Renovation/upgrading of existing electrical, lighting protection, nurses calling system and extra low voltage systems of both main and new ward building of Korea – Sri Lanka Friendship hospital in Matara, Sri Lanka
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
This tender has been posted through the UNOPS eSourcing system. Cet avis a été publié au moyen du système eSourcing de l'UNOPS. Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS.
Link | Description | |
---|---|---|
https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
72101501
-
Handyman services
72101504
-
Disaster proofing or contingency services
72101505
-
Locksmith services
72101506
-
Elevator maintenance services
72101507
-
Building maintenance service
72101508
-
Floor cleaning services
72101509
-
Fire protection system and equipment maintenance or repair service
72101510
-
Plumbing system maintenance or repair
72101511
-
Air conditioning installation or maintenance or repair service
72101512
-
Hoist construction service
72101513
-
Offsite construction service
72101514
-
Refuse area construction service
72101515
-
Subsidence service work
72101516
-
Fire extinguisher inspection maintenance and repair service
72101517
-
Portable generator maintenance and or repair service
72101518
-
Portable generator rental service
72101519
-
Gas fitting installation service
72101520
-
Roof framing service
72101521
-
Building framing service
New clarification added: Question:What does it mean by MULTICORE cable in BOQ item 2P11/C95 - Cu/XLPE/PVC 2.5mm multicore, unarmed circular conductor (out door cable) ?Answer:Electrical Cable for Outdoor Garden/Street light
Edited on:
22-Mar-2019 17:23
Edited by:
webservice@unops.org
New clarification added: Question:What is the backup time for 5 kVA, UPS (1 Phase) in ETU & SEPTIC THEATRE in BOQ item 2P11/C6 and 5 kVA, UPS as per Drawings and specification BOQ item 2P11/C16 ?Answer:30 minutes
Edited on:
22-Mar-2019 17:20
Edited by:
webservice@unops.org
New clarification added: Question:What is the BACKUP TIME for UPS in BOQ item 2P11/C65 & 2P11/C66 ?Answer:30 minutes
Edited on:
22-Mar-2019 17:17
Edited by:
webservice@unops.org
New clarification added: Question 1: Need colored Schematic diagram to rectify the cables ( Fiber,CAT6,CAT5…).Answer 1: In the drawing clearly labeled. Please refer. Question 2: According to the drawing - KSFH-A1-NBRM-DA-01 ; there are 6 Racks. But in BOQ only 4 (1 (42U) & 3 (17U)).Answer 2:Please follow the BOQ Question 3: Switch uplink (Rack to Rack) by Fiber or CAT 6.Answer 3:Fiber Cable Question 4: What is the purpose of 3m UTP Patch cord (2P11/E12). Or how many 3m Patch cords required.Answer 4:Patch cords to be used for connecting switch ports and patch panels Question 5: 2P11/E12 mentioned Patch panel with 24 Keystones, that means 1 patch panel with 24 ports. Actual requirement is five, 24 port Patch panels.Answer 5:Please follow the BOQ Question 6: It is not mentioned about the Fiber patch panel, As in (2P11/E16) If it is only to connect 6 core 124m cable, we need only two Fiber patch panels. Answer 6:Please follow the BOQ
Edited on:
22-Mar-2019 17:14
Edited by:
webservice@unops.org
New clarification added: Question:Sorry, can't find above Drawing No KSFH-A1_EL-07C in the given list.?Answer:Please Refer Drawing No. KSFH-A1-RM-EL-07c in Document “Drawings in Section IV Drawing Part 2 of 3”
Edited on:
22-Mar-2019 17:05
Edited by:
webservice@unops.org
New clarification added: Question:Please give us One week Time Extension to Bid Submission in order to submit Competitive Bid. Answer:UNOPS had already extended the bid submission deadline in 3 Amendments. Due to urgent project needs, we need to finalize this ITB as per the extended deadline which is on 24th March 2019, 09:30 UTC (3:00 PM Sri Lanka time).
Edited on:
21-Mar-2019 15:31
Edited by:
webservice@unops.org
New clarification added: Question:In 2P11/C17 and 2P11/C18 - Sub Distribution Board A/C Plant / Sub Distribution Board Contol Panel Line Dagram not there?Answer:Please refer, “Single line diagram for DB: Chiller plant Control panel” in Drawing No: KSFH-A1_EL-07C
Edited on:
19-Mar-2019 10:28
Edited by:
webservice@unops.org
New clarification added: Question 1 : 2P11/E8 - "Core Switch SFP 16 port unit" , Wher you going to place the switch? is this in ground floor of the old building.Answer 1 : Yes. Ground floor of Existing BuildingQuestion 2 : 2P11/E9 - Is this Switch 16 port or 48 port? where you have gone place the Switch.Answer 2 : This Switch is 48 port and it will be placed in Ground floorQuestion 3 : Above items are end terminal points of Fiber cable or do you want separate Switch for each floor?Answer 3 : Yes, Separate Switch for each floor
Edited on:
18-Mar-2019 12:08
Edited by:
webservice@unops.org
New clarification added: Question:In BOQ item 2P11/D1 is mentioned as Copper Air Terminal as lightning arresrers. But in drawing no KSFH-A1-LPS-01 shows as Early Streamer Emision Type. To which type we should bid?Answer: Follow the BOQ description.
Edited on:
14-Mar-2019 11:43
Edited by:
webservice@unops.org
New amendment added #5: Amendment 05:Revision of the date of the Deadline, Clarifications and upload of revised BoQ .The relevant Contract provisions indicated below are amended to read as follows;Deadline under General:2019-03-24, 09:30 UTC (3:00 PM Sri Lanka time)Clarifications under General:2019-03-22, 09:30 UTC (3:00 PM Sri Lanka time)Bill of Quantity under Documents:Replace the file “ ITB_Minor_work _Construction_Contract_Section_VII_Bill of Quantity “ with " ITB_Minor_work _Construction_Contract_Section_VII_Bill of Quantity_Revision 1 ” and upload of document “ Summary of Changes in BoQ “ under documents.
Edited on:
14-Mar-2019 08:48
Edited by:
webservice@unops.org
New clarification added: Question:Under Public address system following items are not measured in the BOQ but those items are required to complete the system. Do we need to include prices of these items to our bid.Pre-Amplifier Mixer PanelPower Supply PanelEmergency Message Panel21U System RackAnswer:No need to include the prices of said items in the bid.
Edited on:
14-Mar-2019 08:29
Edited by:
webservice@unops.org
New clarification added: Question: Single Line Diagrams have not been provided for the panels mentioned in the BOQ as; “’A/C Plant” and “Control Panel”.Please provide the relevant Single Line Diagrams. Answer: Please refer to drawing KSFH-A1-RM-EL-07C Question: Please let us know under which schedule we need to attach our technical details, Ex: Catalogues of proposed productsAnswer: Bidders are NOT required to submit documents such as Catalogues of proposed products along with the bid. After award the contract (during the contract management stage), selected contractor shall submit product Catalogues/Broachers etc. for the prior approval of employer’s representative.
Edited on:
13-Mar-2019 14:07
Edited by:
webservice@unops.org
New clarification added: Question: MDF is not included in the BOQ. But shown in the drawing, Is it necessary to quote?, If so please mention the capacity.Answer: Need to quote 3' x 3' MDF with krone modules. Need 2 blocks, one for PABX side and other to line side.Question: As per the BOQ there is only 50 pair Intermediate distribution frame. But as per the schematic diagram there are 6Nos of 20 pair JB and 6Nos of 10 pair JBs. Do we need to quote for these items also?Answer: Need 50 pair Intermediate distribution frame, 02 Nos of 20 pair JB and 1 Nos of 10 pair JBs for New Building. Question: In the BOQ there is only 1 No of 48 port Ethernet switch, But in the Schematic diagram there are 05 Nos of 24 port Switches. please clarify?Answer: Need 05 no's of 24 port Switches. 02 no's for New Building and 3 no's for Existing Building.
Edited on:
13-Mar-2019 14:04
Edited by:
webservice@unops.org
New clarification added: Question: 150 mm x 150 mm Cable Ladder & 250 mm x 150 mm Cable Tray are not available in standard sizes, can we quote 150 mm x 75 mm Cable Ladder & 300 mm x 75 mm Cable Tray instead of those.Answer: If the specified sizes are not available in the market, the sizes proposed by bidder should be the nearest size available in the market and should serve the intended purpose.
Edited on:
13-Mar-2019 13:59
Edited by:
webservice@unops.org
New clarification added: Question: Item No. 2P11/E12, 2P11/E13 and 2P11/E14, How to find the required quantity?Answer: Please refer to the additional drawings uploaded through amendment.
Edited on:
13-Mar-2019 13:57
Edited by:
webservice@unops.org
New clarification added: Question: What is the way of taking outside calls (PSTN) ? And how many trunks? (Example: SIP – 10 trunks/channels, CO Direct Lines – 10, E1 Link – 2) Answer: Up-Link Card - 8 line (Direct Line - 8 Nos.), shall Support for E1 link and SIP Connectivity for 10 IP Phones for future expansion. Question: How many IP Extensions to be configured? As mentioned in the document it is needed 10 IP Phones. Is there any specification for IP phones?Answer: 6 IP Extension with 6 Nos. of IP Phone. SIP compatible phone Question: It is have mentioned 100 Analog Extensions to be configured, but the number of phones are not measured in the BOQ?Answer: PABX capacity to 128 channel. Supply 25 Nos Analog Phones.
Edited on:
13-Mar-2019 13:54
Edited by:
webservice@unops.org
New amendment added #4: Amendment 4:Include the file "ITB_Minor_work _Construction_Contract_Section_IV_ Additional Drawing_PA System"The Additional Drawings listed below are included;PA System LayoutPower LayoutPA Schematic Diagram Layout
Edited on:
11-Mar-2019 05:19
Edited by:
webservice@unops.org
New clarification added: Question: For the Public address system, it is critical to quote according to the BOQ without having speaker point locations. Therefore Please provide floor diagrams indicating speaker locations, for both existing and new building with schematic diagram. Answer: Addtional drawings will be posting with Amendment 4 of this ITB.Question: Under supplying of light fittings( BoQ item no: 2P11/C76) Supplying and fixing of Emergency Light with battery back up, Please let us know what type of lighting fixture required, ( wall mounted double head light or any other type fitting with emergency battery kit).Answer: Wall Mounted Emergency LED twin Light with 3 Hrs Battery backup
Edited on:
09-Mar-2019 13:31
Edited by:
webservice@unops.org
New clarification added: Question: Please be kind enough to provide drawings for ELV system and Network system. Those drawings are not inclded in the set of drawings that you have sent.Answer: Amendment 3 for this ITB is posted with provding addtional drawing ELV system and Network system. Refer Document section file name, "ITB_Minor_work _Construction_Contract_Section_IV_ Additional Drawing"
Edited on:
09-Mar-2019 13:07
Edited by:
webservice@unops.org
New amendment added #3: Amendment 03:Include the file "ITB_Minor_work _Construction_Contract_Section_IV_ Additional Drawing"The Additional Drawings listed below are included;Data Telephone Layout Ground FloorData Telephone Layout First FloorData Telephone Layout Second FloorData Telephone Schematic Diagram
Edited on:
09-Mar-2019 06:26
Edited by:
webservice@unops.org
New amendment added #2: Amendment 02:Revision of the date of the Deadline, Clarifications, Bidders eligibility, Checklist and post Clarification Meeting Minutes. The relevant Contract provisions indicated below are amended to read as follows;Deadline under General : 2019-03-17 09:30 UTC (3:00 PM Sri Lanka time)Clarifications under General : 2019-03-14 09:30 UTC (3:00 PM Sri Lanka time)Posted the Clarification Meeting Minutes under “Documents”.Bidder eligibility under “Particulars” will now read as;No nationalities are excluded from submitting a bid. Bidders should have valid business Registration in Sri Lanka.Checklist of documents to be submitted by vendors under “Checklist”Copy of Valid CIDA registration certification will now read as “Copy of Business Registration in Sri Lanka”.
Edited on:
03-Mar-2019 06:14
Edited by:
webservice@unops.org
New clarification added: Question: Kindly request a time extension of two weeks for the tender submission as we need some time to work-out our pricing considering site situationAnswer: Request will be considered and decision will be published through a amendment.Question: Please let us know how or where to include the notes/details related to specific areas in our offer?Answer: If you have a specific notes/details in Technical Documents (Returnable Bid Schedule) you can insert those in the relevant field. Do note that UNOPS will be evaluating based on the set “Evaluation Criteria” under tender information. If the note is related to Financial offer, bidder can include it in Comments field under “Financial offer details” tab.
Edited on:
01-Mar-2019 10:24
Edited by:
webservice@unops.org
New clarification added: Question:kind requesting to extend the closing date (at least 10 to 12 working days) since we need to do the groundwork & preliminary inspection at a site especially on the PA system and telephone system and telephone system Answer:We will consider this request and send an amendment to the tender documents.
Edited on:
27-Feb-2019 08:00
Edited by:
webservice@unops.org
New amendment added #1: Amendment 01:Revision of the date of the Deadline , Clarification Meeting and Site Visit. The relevant Contract provisions indicated below are amended to read as follows; Deadline under General2019-03-07 09:30 UTC (3:00 PM Sri Lanka time) Clarifications under General2019-03-05 09:30 UTC (3:00 PM Sri Lanka time) Clarifications/pre-bid meeting date under Particulars2019-02-26 04:30 UTC (10:00 AM Sri Lanka time) Site visit/inspection date under Particulars2019-02-26 05:30 UTC (11:00 AM Sri Lanka time)
Edited on:
19-Feb-2019 05:52
Edited by:
webservice@unops.org