ITB Construction Contract for Small Works - Supply and Installation of PV Solar System and Street Lighting for Bourj Hammoud Souk Lighting in Lebanon
UNOPS
ITB Construction Contract for Small Works - Supply and Installation of PV Solar System and Street Lighting for Bourj Hammoud Souk Lighting in Lebanon
Invitation to bid
Reference:
ITB/2023/49207
Beneficiary countries or territories:
Lebanon
Registration level:
Basic
Published on:
26-Oct-2023
Deadline on:
20-Nov-2023 07:00 (GMT 0.00)
Description
Tender description: [iSupply and Installation of PV Solar System and Street Lighting for Bourj Hammoud Souk Lighting in Lebanon]
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
This tender has been posted through the UNOPS eSourcing system. / Cet avis a été publié au moyen du système eSourcing de l'UNOPS. / Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS. Vendor Guide / Guide pour Fournisseurs / Guíra para Proveedores: https://esourcing.unops.org/#/Help/Guides
First name:
N/A
Surname:
N/A
Link | Description | |
---|---|---|
https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
72151501
-
Lighting installation services
New amendment added #5: This amendment was raised in order to:Sightly amend some items in the BOQ (changes are highlighted in green) the revised file is available under the documents tab.Replace drawing no. ELE-401-410 with P-2305-BH-ELE-401 to 410 (1) on the same link, which is provided below for ease of refernce. (available under the documents tab as well): https://drive.google.com/drive/folders/1qcyqfYAdPuig4krb21MZG2uBwIYIhko_?usp=sharingOther info, terms & conditions are the same with no change.
Edited on:
16-Nov-2023 12:59
Edited by:
webservice@unops.org
New amendment added #4: This amendment was raised in order to extend the tender deadline to 20 November 2023.Other info, terms & conditions are the same with no change.
Edited on:
13-Nov-2023 00:30
Edited by:
webservice@unops.org
New clarification added: Clarifications:Dear Sir,Regarding the Bid for the construction of Supply and Installation of PV Solar System and Street Lighting for Bourj Hammoud Souk Lighting in Lebanon, ITB ref. No. [ITB/2023/49207], we kindly request your assistance in providing clarifications for the following inquiries:1. Once the project is awarded and invoiced, is it exempt from all direct taxes, including VAT, MoF taxes and any other related charges? Is VAT going to be invoiced?2. Given that we have recently become aware of the project, and that the date of the site visit has already passed, may we request the scheduling of another site visit?3. In section III: Condition of contract, we can’t open the 2 links related to “Instrument of Agreement” and “General Conditions of Contract”. Could you please provide guidance on how to access this information?UNOPS Answer:All bids shall be submitted net of any direct taxes including customs duties, indirect taxes such as sales taxes or VAT, and taxes on commodities, such as fuel (as mentioned under the particulars tab).Please note that a site visit was held on the 2nd of November 2023. You can find the minutes of this meeting on the documents tab. No more visits will be conducted, however, you are free to visit the site anytime. You can find the location under the particulars tab.The links can be opened without any problem, however, you may use the below links if still you are unable to open them:General Conditions: https://drive.google.com/file/d/16--MBdpluDDyHQnYFqNM44y54Dh-Ck2C/view?usp=sharingInstrument of Agreement: https://drive.google.com/file/d/15zzsBvd1uqt-Yg_tSPLQ7C_RLT7Gwo73/view?usp=sharing
Edited on:
12-Nov-2023 08:04
Edited by:
webservice@unops.org
New clarification added: Clarification:Dear Sir/ Madam,The Tender document specifies that all bids should exclude any direct taxes, including customs duties, as well as indirect taxes like sales taxes or VAT, and taxes related to commodities such as fuel. Given that the goods will be imported from overseas and will be subject to taxes and duties, it’s worth noting that only locally purchased goods will be exempted from VAT. Is there a provision for an exemption letter for this project?UNOPS Answer:This project is exempted from taxes mentioned under the particulars tab. Please note that UNOPS will provide a tax exemption letter for the awarded bidder based on submitting the needed documents at that time
Edited on:
12-Nov-2023 07:53
Edited by:
webservice@unops.org
New clarification added: Clarification:Dear team,I hope this email finds you well.Kindly find below the project clarifications:1) It was mentioned on the preliminaries sheet of the BOQ (part 0.13) that we need to install a CCTV system, however that wasn’t mentioned in the BOQ – Kindly Clarify2) As for the Silicon PU Sports Flooring, could you please clarify more on this part3) Regarding Item D in the BOQ section 1.5 (Feeder Pillars) , could you please clarify what do we want to price in this item. Kindly Clarify4) Could you please clarify the reason why each battery bank is connected to one inverter. Why can’t we connect all the bank (156+156 +156) to all the inverters together.5) As for the inverters, could we connect one 150kW inverter or we are obliged to divide them into 3 of 50kW. Kindly ClarifyUNOPS Answer:1) CCTV Cameras are temporary installations, only during the construction phase. Therefore, they will not be under a separate BOQ item.2) The intended usage of the space under the canopy is a sports court. The surface of the roof slab is currently unfinished and non-waterproofed. The proposed PU flooring addresses the water-proofing issue, surface finishing and safeguard against injury from the exposed steel base plate/bolts, and the usage requirements by the beneficiary.3) The feeder pillars are completely new items. The pricing should include the supply and installation of the enclosure, breakers, busbar, and all the items shown on the feeder pillar schedule with all necessary accessories.4)The design has distributed the battery banks and inverters into 3 groups to save on DC cabling, provide more flexibility, and have less risk in case of fire.5) The design intention is to have 3 inverters of 50 KW for the reasons mentioned in item 4 above and also to have less risk in case of damage to one system and to have more choice of inverters suppliers.
Edited on:
12-Nov-2023 07:42
Edited by:
webservice@unops.org
New clarification added: Clarification:Dear Sir,We would appreciate the opportunity to conduct a site visit. Could you kindly furnish us with the details of the timing and location?UNOPS Answer:Please note that a site visit was held on the 2nd of November 2023. You can find the minutes of this meeting on the documents tab.No more visits will be conducted, however, you are free to visit the site anytime. You can find the location under the particulars tab.
Edited on:
12-Nov-2023 07:38
Edited by:
webservice@unops.org
New clarification added: Clarification: Regarding the DC Combiner Box:Can it be Plastic IP65.UNOPS Answer:Metallic enclosures are to be used.
Edited on:
12-Nov-2023 07:34
Edited by:
webservice@unops.org
New clarification added: Clarification: Regarding the Enclosure for Batteries and Inverters:Can the enclosure be 4Mx4M, Height 2.5MUNOPS Answer:As per the design configuration, big-sized enclosures aren't required. However, it is the contractor's liability to propose a size suitable to the proposed solution.
Edited on:
12-Nov-2023 07:29
Edited by:
webservice@unops.org
New clarification added: Clarification:Regarding the Structure:Can it be made of G90 with Zinc Plated and Epoxy Powder Coating instead of Painted steel?Thank youUNOPS Answer:Yes. Structural black steel sections can be replaced with G90 as it is only a matter of coating. The G90 structural steel section properties and tensile strength are to be the same of higher of the design sections shown on the drawings.
Edited on:
12-Nov-2023 07:23
Edited by:
webservice@unops.org
New amendment added #3: This amendment was raised in order to amend the qualification criteria no. 2, to be as follows:"2. The bidder has been registered in Lebanon as a contractor and in continuous business during the last eight (8) years. For JV/Consortium/Association, each partner shall meet this criterion."The amendment was reflected on the criteria tab and the file "Small_Works_ITB_Section_II_III_IV_V - Bourj Hammoud Souk Lighting-rev.2" which is located under the documents tab.
Edited on:
08-Nov-2023 11:36
Edited by:
webservice@unops.org
New amendment added #2: This amendment was raised in order to:Publish the minutes of the pre-bid meeting that was held on 02 November 2023. This file is available under the documents tab.Amend the IP requirement in the (ITB_Technical Specifications Questionnaire-rev.1 file) to 55 minimum instead of 65Remove the requirement of having a manufacturer authorization for PV Modules; Inverters; Energy Storage Systems; and Lighting FixturesOther info, terms & conditions are the same with no change.
Edited on:
06-Nov-2023 11:19
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,This is to remind you of tomorrow's site visit as per the following details.Thank you, Location: St Jack Plaza, Bourj HammoudCoordinates: https://maps.app.goo.gl/vcKdWqyFGwnzGotB9The site visit will be held on 02 November 2023 at 10 a.m. Lebanon time.It is not mandatory, however, bidders are highly encouraged to attend.Bidders who intend to attend should send the name of their representative using the eSourcing clarification tool.
Edited on:
01-Nov-2023 12:45
Edited by:
webservice@unops.org
New amendment added #1: This amendment was raised in order to add the Bill of Quantities file under the documents tab.Other info, terms & conditions are the same with no change
Edited on:
31-Oct-2023 15:10
Edited by:
webservice@unops.org
New clarification added: Clarification:Dear SirWe had Check Tender Document but there are no BOQ , kindly Provide us with the BOQ.UNOPS Answer:The BoQ file was added under the documents tab. You will be able to find it after releasing amendment no. 1 (soon)
Edited on:
31-Oct-2023 08:34
Edited by:
webservice@unops.org