CANCELLED The Construction of FAO Office Building, Phnom Penh, Cambodia
UNOPS
CANCELLED The Construction of FAO Office Building, Phnom Penh, Cambodia
Invitation to bid
Reference:
ITB/2020/16296
Beneficiary countries or territories:
Cambodia
Registration level:
Basic
Published on:
14-Oct-2020
Deadline on:
06-Nov-2020 08:00 (GMT 0.00)
Description
The works include the Construction of FAO Office Building, Phnom Penh, Cambodia.
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
This tender has been posted through the UNOPS eSourcing system. / Cet avis a été publié au moyen du système eSourcing de l'UNOPS. / Esta licitación ha sido publicada usando el sistema eSourcing de UNOPS. Vendor Guide / Guide pour Fournisseurs / Guíra para Proveedores: https://esourcing.unops.org/#/Help/Guides
First name:
N/A
Surname:
N/A
Link | Description | |
---|---|---|
https://esourcing.unops.org/#/Help/Guides | UNOPS eSourcing – Vendor guide and other system resources / Guide pour fournisseurs et autres ressources sur le système / Guía para proveedores y otros recursos sobre el sistema |
72111111
-
General residential construction contractor service
Tender cancelled on 2020-12-04 07:00 UTC. Dear Bidder,Please be informed that the tender has been cancelled due to non of the bid received are compliant to the qualification criteria stated in the ITB documentation.With best regards,Bid Evaluation Commitee .
Edited on:
04-Dec-2020 08:00
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Regarding to the ceiling specification, it is Gyproc Gyptone ceiling panel with 600x600mm( 9mm thk) white finishing and the support Grid: Gyproc 38T15Regards,UNOPS Cambodia
Edited on:
03-Nov-2020 07:39
Edited by:
webservice@unops.org
New clarification added: Dear Bidder,Kindly see below question and anwer related as per below:Q: Is it possible to request Façade drawing Back, Front, and Rear View?We cannot find these views in the set.A: You can see the architect drawing at Seq No 1000,1001, 1002 and 1003, file name: ITB_Short_Form_Construction_Contract_Section_IV_Annex C. DD-Architecture_part 1. With best regards,UNOPS Cambodia
Edited on:
02-Nov-2020 04:33
Edited by:
webservice@unops.org
New amendment added #1: This amendment is made to upload the minute of pre-bid meeting and presentation slide during the meeting held on 23rd October 2020 at 9:30 AM Cambodia local time.
Edited on:
28-Oct-2020 01:51
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Kindly see the below question and answer to the querry as per below:Question: S/NO.14 Air-Cooled Split Air-conditioning Units, Acceptance Brand are: Daikin, Mitsubishi, Panasonic But in the BoQ 1.4 MVAC the brand of AC is Gree which not included in the MEP specification. So, which one is acceptible?Answer: The brand of AC has to follow the Brand of Equipment listed in Specification (Daikin, Mitsubishi, Panasonic). Please put your products with price in the BoQ.With best regards,UNOPS Cambodia
Edited on:
27-Oct-2020 07:29
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Kindly find our repsonses to each of your questions as per below:Q1.Regarding to the location of existing building that we will remove, it will be cast new concrete slab ? please advide us?A1. New concrete slab is required for existing building after demilition, Please add and highlight the cost in prelinainary cost.Q2.In BOQ No.2 External works we saw at remark put Phase II, so this BOQ will put the price for this tender submission or not ? Please advide us?A2. Reguarding External work in BoQ marked Phase II, please put price for all work items. 3. Would we upload bid submission as PDF files with sign and stamp or just excel/work files without sign and stamp?A3. The bid submission forms and other required returnable forms should be signed, stamped and upload in the system in the form of PDF file.With best regards,UNOPS Cambodia
Edited on:
26-Oct-2020 03:22
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Thank you for your query.Q: May we can pay the site visit by contact any persons on Monday beside the indicated date and time?A: You can manage to visit the site on your own. The site location is located in the compound of the Ministry of Agriculture, Forestry and Fisheries. The address: # 200 Preah Norodom Blvd (41), Chamkarmorn, Phnom Penh, Cambodia. Kindly refer to the site location as per drawing. With best regards,UNOPS Cambodia
Edited on:
23-Oct-2020 09:38
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Please kindly inform that the meeting room for our pre-bid meeting have been changed from Room no. 511 on 05th Floor to Room no. 628 at 06th Florr at the same time and location at 9:30am on Friday 23th October 2020 at UNOPS office, Phnom Penh Center Building A, Sothearos Blvd., Phnom Penh, Cambodia.With best regards,UNOPS Cambodia
Edited on:
22-Oct-2020 04:50
Edited by:
webservice@unops.org
New clarification added: Dear Camatec Engineering and Construction Co.,Ltd Team,Thank you so much for the confirmation of your participation in the pre-bid meeting and site inspection. Kindly join the meeting at UNOPS meeting room no.628, 06th Floor, Phnom Penh Center Building A, Sothearos Blvd., Phnom Penh, Cambodia.With best regards,Dany
Edited on:
22-Oct-2020 04:25
Edited by:
webservice@unops.org
New clarification added: Dear Bidders,Thank you for your query, kindly see our responses to your points as per below: (1) The Footer of Contract Templates cover (Page1): Date [insert month] 20[insert] (Q) Please provide the exact date to insert or specific the [insert]?A1: The exact date will be added at the contract signing stage only. The templates provided in the tender docuemnts serves as information for the bidders to aware and accept about our contract term and conditions in case of award only. (2) Built Drawing in the BOQ as Lum Sum, is for a new drawing upon the actual work occur?A2: Yes, the contractor is responsible to provide as-built drawing ( revised set of drawing) upon completion of construction. (3) In relation to the insurance and construction permit. Does this project has the consulting firm/consultant?A3: We hired a design firm for the detail design. The project owner is responsible for construction permit. UNOPS Project Manger is responsible for managing and supervising the construction contract. For construction insurance, the contractor has to comply with the contract.(4) May I request to have a site visit on 23/10/20 14:00? If you are okay, please give me the contact person for a visit.A4: We already set the exact timeline on 23 Oct 20 at 11:00 AM right away after pre-bid meeting.(5) Bid Security, regarding the content of clause 16. Bid Security which shall be in the form set out in Returnable Bid Schedule 2 - Form of Bid Security, but in the Returnable Bid Schedule 2 is written "NOT USED". Mean, the bidder shall not issue the Bid Security?(A5) The bid security is not a requirement under this tender submission. Only perforance security is required for the successful bidder.With best regards,UNOPS Cambodia
Edited on:
21-Oct-2020 09:55
Edited by:
webservice@unops.org
New clarification added: Dear Bidder,Thank you for your query, kindly see our responses to your points as per below: (1). Financial report has to be audited to demonstrate it's authenticity. (2). Construction permit is the responsibility of the project owner/employer. The contractor must have legal documents, registration and licenses to carry out the work in accordance to the contract.(3). The payment will be made according to the payment schedule identified in the contract template, the employer has reserved sufficient budget to release to the contractor on time if the work is completed according to time frame and specification as in the contract. With best regards,UNOPS Cambodia
Edited on:
15-Oct-2020 11:04
Edited by:
webservice@unops.org